Evaluating the Performance of Environmental Streamlining:
Development of a NEPA baseline for Measuring Continuous Performance
1.0 INTRODUCTION
|
Index
| Next
1. 1 Background
The National Environmental Policy Act of 1969 (NEPA) marked the beginning of
the environmental review process for all federal actions, including the use
of federal funds for construction of highway and bridge projects falling under
the purview of the U. S. Department of Transportation, Federal Highway Administration
(USDOT / FHWA). Under NEPA, applicable projects are assessed in relation to
the environmental conditions of the area, and the impact that various project
alternatives would have upon those environmental conditions. It has always been
the intent of the NEPA process to ensure that informed decisionmaking with respect
to the environment occurs when considering the need for, and proposed alignment
and design of transportation projects.
Despite the overall benefit of NEPA in addressing the wide array of public
interests that can be impacted in some manner by transportation decisions, the
process has long been criticized due to the perception that it is a major source
of delay and inflationary cost increases by the time that projects are actually
constructed and open to traffic. This perception is especially true when an
Environmental Impact Statement (EIS), which is the most comprehensive and time-consuming
environmental document required under NEPA, is involved.
The perception that NEPA results in extensive delays and additional costs to
the successful delivery of transportation projects is further magnified when
environmental processes pursuant to other laws and regulations are also required
and addressed under the overall NEPA umbrella. For instance, regulations such
as Section 4(f), Section 106, and Section 7 which have their own special requirements
but are generally performed concurrently with NEPA, can complicate a project's
progress if the applicable resources (i.e. , public parks and recreation areas,
significant historic and archaeological sites, and threatened and endangered
species, respectively) are present and potentially impacted. In addition, Section
404 permits regarding wetland impacts may be initiated during the NEPA process,
but they are generally not completed until after NEPA has been completed due
to the greater level of design detail needed to complete the permit applications
in comparison to that required for preparing a NEPA document. Reviews by agencies
such as the U. S. Army Corps of Engineers, the U. S. Fish and Wildlife Service,
the U. S. Coast Guard, and the U. S. Environmental Protection Agency, as well
as various state regulatory and review agencies, add further to the perception
that extensive delays and additional costs occur, even though such reviews are
more often affiliated with permitting processes than NEPA. Of course, the amount
of public and political opposition to a project can also have a significant
impact on schedule and cost.
The reality is that over the 30 years since NEPA was implemented, transportation
planners and engineers have questioned the effect that the NEPA process has
had on the timely delivery and overall cost of transportation projects. Although
it is a commonly accepted fact that the NEPA process, especially the preparation
and approval of EISs, can often take several years to complete, the time required
and the relative costs incurred to complete the entire highway project delivery
process has not been well documented or understood. At best, studies of the
environmental process have looked at that process directly, but generally not
relative to the construction or other phases of the project. Most of the information
available concerning the time required to complete a project has come from anecdotal
sources, generally focused on single projects. In this regard, it is not evident
what portion of the schedule and cost of the entire project delivery process
is attributed to NEPA compliance requirements, in comparison to other potential
sources of process delay such as funding shortages, compliance with environmental
permitting requirements, changes in design, contractor delays, lawsuits and
injunctions, etc. Until the impact of NEPA on the transportation project delivery
process can be better quantified, it is likely that the popular perception that
NEPA comprises a major source of delay and inflationary cost affecting the ability
to deliver transportation projects on schedule and within budget will continue
to exist.
1. 2 Relationship of NEPA Process to Total Project Delivery Process
Before the impact of the NEPA process on overall timing and cost of project
delivery can be assessed, it is important to understand how NEPA integrates
into the overall project delivery process. For purposes of this study, the project
delivery process begins at the time that a project is advanced from a planning
phase to an actual committed project, which may or may not begin with the inclusion
of the project on a Transportation Improvement Program (TIP) or a State Transportation
Improvement Program (STIP). Given the fact that NEPA has been in existence for
30 years and the transition between planning and project development has been
somewhat variable during that period, it can generally be assumed that project
development begins when federal funds are first allocated at a project level,
which usually begins with preliminary engineering.
The elements that are generally considered to be included as part of the full
project delivery process are: preliminary engineering, final or construction
engineering, right-of-way acquisition, and construction. These four major elements
have historically been used and recorded as part of FHWA's Fiscal Management
Information System (FMIS) which is a financial database of all highway projects
dating back to the 1940s that have been financed using federal funds. Other
elements of the overall process such as scoping and NEPA environmental documentation
also exist, although they would likely be integrated into one of the four basic
elements such as preliminary engineering. Environmental permitting is another
element of the overall process, although that element would also likely be incorporated
into one of the four basic elements such as preliminary engineering or, more
likely, final engineering.
Due to the fact that NEPA compliance fits into the overall project delivery
process as a subset of one or more of the four major elements of the process,
the time that it takes to fulfill all of the requirements of NEPA naturally
could have a direct impact on the timing of the overall process. Any delays
in receipt of a Record of Decision (ROD), which is the final official step of
the NEPA EIS process, could also impact upon the cost of the project delivery
if the delays are extensive enough for inflationary cost increases to result.
Any inflationary cost impacts would be in addition to the direct cost of complying
with NEPA in terms of the actual preparation of the necessary alternatives analyses
and environmental studies. However, as stated in Section 1. 1 above, the direct
effect of NEPA compliance on the ultimate schedule and cost of delivering a
completed transportation project is unclear at this time, given that other factors
can also contribute to the schedule and cost.
1. 3 Purpose of Research Study
The purpose of this research study, from the outset, has been to provide a
better understanding of the impacts of the NEPA process on the total time and
cost involved in delivering a federal-aid highway or bridge project to construction
completion. Due to the common perception that NEPA compliance is a major source
of delay and inflationary cost increases on such projects, this research was
designed in an effort to identify the true schedule and cost implications of
NEPA upon the total project delivery process. It has also been the intent of
this study to identify the individual factors influencing the amount of time
required for the NEPA process for individual projects in order to develop performance
measures.
The impetus for this research is directly related to Section 1309 of the Transportation
Equity Act for the 21st Century (TEA-21), which directs the Department
of Transportation to develop a coordinated environmental review process under
the heading of environmental streamlining. Given widespread concerns
about delays, duplication of effort, and additional costs associated with NEPA
and other environmental review processes, the law specifically states that:
"The Secretary shall develop and implement a coordinated environmental
review process for highway construction projects that require. . . the preparation
of an environmental impact statement or environmental assessment under the National
Environmental Policy Act of 1969 (42 U. S. C. 4321 et seq. ), except that the
Secretary may decide not to apply this section to the preparation of an environmental
assessment under such Act. . . . "
In response to the overall intent and requirements of the Section 1309 regarding
environmental streamlining, a National Memorandum of Understanding between seven
key federal agencies was agreed upon and signed in July 1999. One of the specific
goals agreed to among the agencies was to "establish, with stakeholder
input, goals, performance measures, and benchmarks to evaluate transportation
and environmental decision making" as part of the effort to reduce project
delays.
In order to begin to develop goals, performance measures and benchmarks for
evaluating future efforts to implement environmental streamlining techniques,
it is first necessary to establish a baseline against which to assess those
future efforts. Since NEPA is at the center of the several environmental processes
that are generally required to be addressed when constructing or otherwise improving
federal-aid highways, NEPA was identified as the process to focus upon for establishing
such a baseline. Although EISs represent only a small component of total NEPA-compliance
studies undertaken by FHWA in recent years, a trend that is expected to continue
in future years as well, projects requiring an EIS tend to have the greatest
potential to experience future improvement pursuant to environmental streamlining.
Therefore, the focus of this research to establish a baseline against which
to assess future environmental streamlining efforts has been directed toward
EIS projects. EIS projects have also been targeted for this research due to
their increased data availability in comparison to lower-level NEPA projects
such as those requiring environmental assessments (EAs) or categorical exclusions
(CEs). To the extent that data was found to be available for these lesser environmental
projects, it was also the intent to include them in the research as much as
possible.
As part of the development of the baseline condition, it has been the specific
intent of this research to identify what component of the time and cost of the
overall project delivery process is attributed to NEPA. In this manner, an indication
of the historical time and cost relationship of NEPA to the overall project
delivery process could be established so that any future streamlining improvements
upon those relationships could be determined. It has been the intent from the
outset to establish this baseline relationship from a random sample of projects
using a statistical approach.
Another basic goal of this research has been to identify and assess a wide
variety of factors and conditions that may have a direct or indirect impact
upon the NEPA process and the project delivery process as a whole, and to determine
the predictive strength of the relationship between NEPA and those factors.
For instance, if it can be determined that such factors as location of a project,
type of project, or types of impacts have a statistical relationship to the
amount of time and cost required for complying with NEPA, which in turn impacts
upon the entire project delivery process, then a predictive tool can be developed
in planning future projects. In this manner, reasonable time frames and costs
associated with the NEPA process under a variety of conditions could be identified
and used in assessing the likely time and cost to be expected for future projects
under similar conditions. Essentially, the baseline condition, against which
all future streamlining efforts would be assessed, must reflect the specific
factors that influence an average time and cost for complying with NEPA,
thereby creating separate baseline conditions for projects exhibiting like characteristics.
Once the separate baselines can be established, then any variations in time
or cost associated with future projects exhibiting similar conditions could
then be measured and assessed. The ability to monitor variations in time or
cost against the baseline condition would, in turn, lead to the ability to assess
future progress in meeting the goals of the environmental streamlining initiative.
A final purpose of this research has been to identify appropriate data sources
and formats that could be utilized for developing the baseline conditions, as
well as for monitoring future progress of environmental streamlining. Any potential
improvements to the existing data or to the collection of future data that would
be appropriate or necessary for carrying forward with this research should also
be identified in this regard.
Therefore, the basic purpose of this research can be summarized with the following
three objectives:
- To develop a methodology that establishes a historical and statistically-generated
baseline of the length of time required to comply with the NEPA process;
- To develop a methodology for statistically assessing the impact of the
NEPA process on project delivery time and cost under a variety of conditions,
and which can be expanded and refined over time in order to monitor future
progress in meeting the goals of the environmental streamlining initiative
of TEA-21; and
- To identify future data needs and improvements for continuing this research
in the future.
|
 |