Evaluating the Performance of Environmental Streamlining:
Development of a NEPA baseline for Measuring Continuous Performance
2.0 SUMMARY OF RELATED RESEARCH
|
Previous
| Index | Next
There have only been a few studies of note conducted during recent years that
examined the time period and/or cost required for the delivery of transportation
projects, or examined what component of that entire time period or cost is attributable
to the NEPA process. Some of the key research studies in this regard to date
are presented below. It should be noted, however, that these studies do not
necessarily reflect a complete bibliography of related research.
Most of the research in this regard has been conducted out of concern expressed
in Congress about the amount of time and money expended on the NEPA process,
and how much that process impacts upon the cost and delivery time of highway
projects. For instance, the General Accounting Office (GAO) presented a report
to Congress in 1994 concerning the effects of the NEPA and Section 404 permitting
processes on the implementation of highway projects, as well as any differences
in those effects resulting from attempts to integrate both processes. [1]
In reality, the GAO study was an effort to evaluate the ability to assess reductions
in delay attributable to several regional environmental streamlining initiatives
that existed even before the environmental streamlining initiative of TEA-21
was enacted.
The GAO study stated that "on most highway projects, FHWA and the states
have taken from 2 to 8 years to complete the NEPA and section 404 reviews. "
As part of the study, seven FHWA divisions and 13 state DOTs were surveyed,
resulting in the identification of 76 highway projects for which environmental
reviews were conducted and completed during the 1988 - 1993 period. The study
concluded that the average NEPA review process among all 76 projects took 4.
4 years. Of that total, 32 projects also required Section 404 permits, and averaged
5. 6 years to complete both the NEPA and Section 404 permit reviews under separate
review processes. No information regarding the length of only the NEPA process
for the 32 projects requiring Section 404 permits was presented in the study.
The GAO study notes that "although the agencies have developed the integrated
processes to expedite the NEPA and section 404 reviews, they have not developed
a system to evaluate their success. " The need for baseline data on the
amount of time needed to complete reviews under the traditional processes was
noted, as was the need for developing plans to track projects' time frames under
the integrated processes. The average time frames established in that study
for the NEPA and combined NEPA and Section 404 processes were developed to satisfy
the need for a baseline condition against which to track and compare time frames
associated with an integrated review process. On the other hand, insufficient
data existed at that time to develop an average time frame for the integrated
process, although the study did establish a basic framework for evaluating the
integrated process in the future.
A study published in 1997 by the North Carolina State University's Center for
Transportation and the Environment (CTE) assessed the costs of environmental
compliance for highway projects, including the NEPA process. [2] This study has probably been the most
rigorous attempt to quantify the impact of the NEPA process on highway project
cost, and specifically states that "all past economic analyses of the costs
of environmental regulations have completely overlooked their impacts on the
construction and repair of highways. " It does note, however, that state
transportation department engineers have suggested in other studies that the
additional costs attributed to environmental compliance are at least 8 to 10%
of the construction and repair expenditures for Federal Aid projects.
The CTE study involved a survey of environmental officials at 50 state departments
of transportation, from which a total of 19 responses were received. The survey
questionnaire requested a variety of information regarding expenditures for
Federal Aid and state projects involving either new construction or repair,
along with the percentages of each that were attributed to environmental compliance
activities. It was found that most survey respondents were unable to provide
the requested environmental compliance cost information. Of those states that
did keep records on staff time and compliance costs, the additional costs were
generally found to be less than 10 percent. However, the survey response was
considered to be too small to be statistically valid, and of limited use.
The importance of the Section 404 permitting process in terms of affecting
the cost of highway projects was demonstrated as part of the CTE study. The
study found that several other project circumstances also varied positively
with project cost, including the number of National Priority hazardous waste
sites, sites on the National Register of Historic Sites, the presence of threatened
or endangered species, membership in conservation groups, and acres of farmland.
The CTE study concludes that concentrations of environmentally-sensitive resources
can impact on time delays and project cost. However, the study was not able
to determine the full extent of environmental compliance costs, and the difficulty
of isolating the costs of the separate factors and regulations as percentages
of the total for uniform application to all projects was noted.
In a separate and recent effort to initiate the development of a baseline condition
that can be used in evaluating future environmental streamlining efforts, FHWA
has reviewed and compiled time frame data for EIS projects completed with a
Record of Decision (ROD) in 1998.
Starting points for these projects were linked to the date that the Notice of
Intent (NOI) was announced. Of the 37 projects that fell into this category,
13% took 10 or more years to complete NEPA; 19% were completed in 7 - 10 years;
16% were completed in 3 years or less. The majority of the projects (51%) took
4 - 6 years to complete. For the total of 37 projects with RODs signed in 1998,
the average amount of time elapsed between the NOI and the ROD was found to
be 67 months, or 5-1/2 years, while the median value was found to be 5 years.
Similar to the EIS baseline effort, FHWA also conducted a study to initiate
a baseline timeframe for projects involving a Finding of No Significant Impact
(FONSIs) or a Categorical Exclusion (CE). This database was compiled from information
provided by 27 FHWA Division offices. Of these, 18 divisions, or 70% of the
respondents, indicated that it generally takes less than 2 years to process
a FONSI, while an additional 8 divisions, or 34%, indicated that it generally
takes between 2 to 3 years. In the case of CEs, 22 divisions, or 85% of respondents,
indicated that it takes less than one year to process a CE, with 18 of them,
or 70%, indicating that it takes less than 6 months. Based on the responses
received, FHWA has estimated that the typical time frame for completing a FONSI
is about 18 months while the typical time frame for completing a CE is 6 months.
Of the three sets of FHWA time frame estimates, only the EIS data are actually
based on file searches and specific starting points (i. e. , NOIs). The FONSI
and CE data are not based on detailed file searches on the part of the participating
FHWA divisions, but rather reflect general experiences and opinions of the respondents.
All three data sets reflect only those specific projects reported to be completed
in 1998. Regardless of these disclaimers, the time frame estimates developed
represent reasonable baseline conditions for use in evaluating future environmental
streamlining efforts, at least until more extensive baseline data can be collected
and analyzed.
Another recent study undertaken in an effort to identify and assess delays
related to the NEPA process was prepared for the American Association of State
Highway and Transportation Officials (AASHTO) and the National Cooperative Highway
Research Program (NCHRP), although that study focused exclusively on Categorical
Exclusions (CEs) and Environmental Assessments (EAs). [4]
In order to collect data on the subject, a total of 40 state departments of
transportation (DOTs) were solicited, of which, 33 responded. According to the
respondents of the survey, a majority of the DOTs experience some CE and EA
process-related delays, even though such levels of environmental documentation
are typically associated with projects resulting in less significant environmental
impacts than EIS projects. Of those DOTs that responded to the survey, 63% reported
some delay with CE preparation and 81% reported some delay on EA projects. In
those states responding, it was estimated that 31 to 48% of all CEs are affected
by delays, while 43 to 64% of all EAs are affected by delays. Given that CEs
and EAs comprise almost 99% of all NEPA projects undertaken by the state DOTs,
it was concluded that a significant number of projects can be affected by delay.
It was also concluded from the AASHTO survey that, on average, delays approximately
triple environmental review processing time from an average of about 8 months
to just under two years for CEs, and from 14 months to about 3. 5 years for
EAs. This conclusion was based on information provided by the respondents for
a total of 101 CE and EA projects where the actual approval took longer than
the timeframe considered to be reasonable. It was further determined that the
three environmental compliance requirements that contribute the most to delays
in preparation of both CEs and EAs are Section 4f (public parks and recreation
areas, and historic resources), Section 106 (historic and archaeological resources)
and Section 404 (wetlands) processes, identified as contributing factors to
delay by 66%, 61% and 53% of the responding states, respectively.
It should be noted that most of the research studies discussed above are based
on data, estimates and opinions provided by survey respondents, and that the
key information provided by the respondents was not statistically-developed
or validated. In the case of the FHWA's EIS baseline research, the data is based
on actual recorded data for all 37 EIS projects completed in 1998, but no information
on the many EIS projects completed in all of the other years since implementation
of NEPA is included. Also, with the exception of the CTE study, none of the
studies actually attempted to assess the impact of NEPA process delay on the
overall project development process or its individual components.
Even though the information in all of the previous studies does provide some
basis for quantifying the impacts of typical NEPA process delays on schedule
and cost of the project development process, the lack of statistical basis for
those findings is somewhat limiting. All of the above studies acknowledge the
fact that quantifiable data for conducting a more detailed statistical analysis
is not readily available, and would require extensive effort in order to collect
and analyze such data in a statistical fashion. Despite this limitation, all
of these studies represent a starting point for establishing a baseline condition
against which to evaluate future environmental streamlining efforts.
|
 |