Evaluating the Performance of Environmental Streamlining:
Development of a NEPA baseline for Measuring Continuous Performance
3.0 RESEARCH APPROACH
|
Previous | Index | Next
3. 1 Research Approach Overview
This research study has been designed in order to provide a more comprehensive,
less subjective, and statistically-based approach to identifying NEPA process
delays and evaluating their impact on time and cost of the overall project delivery
process than any other research effort to date. It has been the intent of this
study from the outset to analyze NEPA process delay implications from a very
broad historical and geographical perspective, and to focus only on those projects
that have actually been delivered in their entirety (i.e. , constructed and
fully operating). It has also been the intent of this study to utilize several
existing and extensive data sets in a manner that would allow at least some
statistical analysis of the information in those data sets to be conducted on
an essentially random sample of projects taken from the total known universe
of relevant projects.
Given the complexity and untested feasibility of using these separate data
sets, especially in conjunction with each other, a limited sampling of projects
was first selected in an effort to test the data in a meaningful way. On the
basis of the preliminary research, a Data Collection Strategy Memorandum
(Louis Berger & Associates, Inc. , March 2000) was prepared to identify
an approach that could provide all of the necessary data for undertaking the
greater research effort. Three primary sources of data useful to the proposed
research were identified and assessed:
- Northwestern University's Transportation Library EIS Database — This database
consists of over 4,000 EIS documents prepared for FHWA projects around the
country, and purportedly includes every FHWA EIS prepared since the inception
of NEPA;
- FHWA's Fiscal Management Information System (FMIS) Database — This database,
which contains more than 3 million records and includes a variety of financial
appropriation information for all highway projects that have been financed
using federal funds since the 1940s, comprises part of FHWA's overall accounting
system; and
- Publicly-Available Internet and Commercially-Available Software Aerial
Photo and Mapping Databases — These data sets include: (containing aerial
photography since 1980 and USGS topoquads); (containing localized mapping
based on U. S. Bureau of Census Tiger Files from 1990); and MapPoint 2000
CD ROM (containing more detailed, larger scale mapping based on U. S. Bureau
of Census Tiger Files from 1990).
Of these, the EIS documents provided the means for collecting detailed information
about each project included in the sample set such as proposed improvements,
environmental conditions and impacts, duration of the NEPA process, etc. The
FMIS database, in contrast, provided detailed information about dates, types
and amounts of appropriations for specific project segments, and provided the
ability to assess individual phases of the project development process. Finally,
the aerial photo and mapping databases provided the means to ascertain whether
or not a project has been fully constructed as proposed in the EIS.
From the preliminary research that was conducted, it was concluded that the
three database sets together could, in fact, provide most of the data that was
pertinent to the overall research study. However, it was also concluded that
integrating them on the basis of individual EIS projects is confusing, complex
and extraordinarily time consuming. Despite the difficulties, it was further
concluded that these databases, used in combination, provide the best opportunity
to develop a comprehensive, thorough and objective set of data that can be used
in creating a statistical baseline for depicting the NEPA process and its relationship
to the overall project delivery process. Details of the process required for
integrating the three database sets according to individual EIS projects are
provided in Section 3. 5 of this report.
It should be noted that it was the original intent of this research study to
evaluate all three levels of NEPA documentation (i.e. , EIS, EA/FONSI, and
CE) in terms of delay. However, it was determined that only EIS projects can
be identified from a centralized database. Unlike in the case of EISs where
the Northwestern University World Wide Web site provides a list of all EISs
prepared by FHWA and the Northwestern University Transportation Library makes
those EISs available for review, no such central source of information or readily
available repository of EAs/FONSIs or CEs exists. In conducting the preliminary
research, one FHWA division office was contacted in order to identify what happens
to EAs/FONSIs and CEs upon completion of design of such projects. According
to that particular office, the environmental documents are included in hard
copy along with design documents and sent to a national archive in St. Louis,
Missouri. Other archive locations for storing similar documents have also been
noted to exist elsewhere in the country. It was implied that these documents
are not generally maintained at the FHWA division offices after a project is
completed and that they are put into permanent storage at one of these archive
facilities. The ability to identify and retrieve such documents would be problematic,
at best.
Given the apparent inability to access EA/FONSI and CE documents from any known
sources, it was ultimately decided that this study should focus only on EIS
projects. This decision also makes sense from a statistical perspective. A sample
size of 100 projects had been predetermined to be used for this study since
such a sample was considered to be sufficiently large to avoid sampling error.
However, if that sample size was disaggregated to include all three levels of
environmental documentation, then the sample for any one of the individual levels
of NEPA documentation would not be large enough to protect against the potential
for sampling error.
The decision to focus on EIS projects exclusively also makes sense from a practical
standpoint. Even though the number of EISs that are prepared for Federal aid
highway projects is dramatically fewer than the number of EAs/FONSIs and CEs
prepared, the length of time required to comply with NEPA's EIS requirements
is inherently greater. Therefore, the implication for the overall project development
process in terms of delay time and cost is also greater when an EIS is involved.
Despite the fact that preliminary research was conducted on a select few projects
in order to assess whether the basic methodology and the several sets of available
data were usable and manageable, the full magnitude of the effort could not
have been realized until the overall research study was underway. The most complex
part of the study turned out to be the data collection element. Details of the
problems and methods used in collecting the full range of data for the 100 sample
projects are discussed throughout Section 3. 5 of this report.
The basic steps of the overall methodology used in this study, in the order
that they were followed, are presented below:
Sample Selection
- From the list of EIS projects available from Northwestern University's
World Wide Web Site, select a stratified random sample of 100 EIS projects
to study, taking both geographic region and decade of each project into account;
Data Collection
- Obtain and review the EIS document(s) associated with each potential project
to be included in the sample in order to identify locational and component
parameters of the project;
- Obtain, parse and review FMIS Type 1 records, and match the appropriate
records to each EIS project;
- Identify whether or not each EIS project has been fully constructed using
information included in the appropriate FMIS Type 1 records and from the aerial
photos and mapping available from the internet and CD ROM software;
- For those projects determined to be constructed, obtain, parse and review
FMIS Type 2 records, and match the appropriate records to each EIS project;
- Record relevant data from all FMIS Type 2 records associated with each
EIS project, and consolidate and record data on the basis of each EIS project
as a whole;
- For those projects determined to be constructed, review the associated
EIS document(s) to collect relevant project, environmental, and NEPA process
data, and record the data on a project data form;
- Enter all relevant project data collected from the FMIS records, the EIS
document(s) and aerial photography / mapping into a computerized database,
and provide visual quality control checks for anomalies in the entered data;
Sample Selection Finalization
- Repeat the above steps until the total sample size of 100 constructed projects
has been completed, taking from the next set of projects on the stratified
random sampling list, as necessary;
Statistical Analysis
- Perform descriptive statistics analysis, including maximum and minimum
values and, in some cases, frequencies, to identify additional anomalies in
the data and to establish descriptive parameters of each data variable;
- Perform exploratory data techniques to look for differences in descriptive
parameters among different FHWA regions;
- Create new data variables as necessary to complete statistical analysis
by manipulating entered data variables;
- Examine data for normalcy of distribution and, where feasible, appropriate
and necessary, transform data to obtain surrogates with a normal distribution;
- Test for differences among FHWA regions with regard to length of the NEPA
process and other variables;
- Examine correlations between NEPA process time and other data variables;
and
NEPA Process Baseline Development
- Utilizing the results of the statistical analysis, identify a NEPA process
baseline or set of baselines under various conditions against which to evaluate
future environmental streamlining efforts.
Tracing through the individual steps presented above provides a general indication
of the overall methodology utilized in undertaking this research study. However,
each of the individual components of the process involved its own set of substeps
and analyses. A detailed discussion of each of these steps, including data limitations
and problems encountered, is provided in subsequent subsections of this report.
3. 2 Description of Data Sources
As mentioned in Section 3. 1 above, there were three basic sources of data
used for undertaking this research (i.e. , Northwestern University Transportation
Library, FMIS Records, and on-line and commercially available aerial photo /
mapping services). The composition, format and availability of these data sources
are discussed in detail below.
3. 2. 1 Northwestern University Transportation Library
The Northwestern University Transportation Library and its World Wide Web site
served as the starting point for undertaking this research. The library contains
more than 4,000 EIS documents prepared for Federal-aid highway projects, dating
back to 1970 when the requirements for NEPA documentation first went into effect.
Since these EISs are purportedly available for all such projects undertaken
in the last 30+ years, the projects covered by these EISs essentially form the
total universe from which to draw the study sample. In this manner, the Northwestern
University Transportation Library was really the backbone of the research.
The Library's internet on-line service provided a complete listing of FHWA's
EIS projects that could be requested by state. The internet address at the time
that most of the research was being conducted was It should be noted, however,
that toward the end of the intense data collection process, the internet address
changed to The ability to specifically request FHWA EIS data by state also became
more difficult following the change in address and format of their web site.
If the entire data collection effort for this project had occurred after the
internet web site changed, the complexity of obtaining the EIS information in
a usable way would have made it virtually impossible to continue.
The EIS database available at the time of conducting the research included
the following information for every project: Title, Agency, State, EPA Number
and Call Number, with an additional line for Notes which was usually blank.
A sample printout of the EIS database requested according to state is provided
in Appendix A.
As mentioned above, the complete on-line database was used to formulate the
universe from which to select a stratified random sample for this research.
Further discussion of the process used for selecting the research sample is
provided in Section 3. 4 of this report.
In addition to serving as the sample universe, the on-line database provided
the mechanism for requesting the actual EIS documents from the Library. After
the potential sample EIS projects were identified, a system was established
with the Library whereby e-mail requests were made for a set of documents. Initially,
only five EISs could be requested and borrowed at a time, but eventually, the
Library permitted EISs to be requested and borrowed for all projects within
a given former FHWA region. The EIS documents available for loan from the Library
generally included the Draft EIS, Final EIS, Supplemental Draft and/or Final
Draft (as appropriate) and often, Technical Appendices. After receiving the
requested documents through the mail, they were kept on loan for purposes of
review for periods of up to a month before having to return them. This system
continued until the entire research sample of 100 projects was selected.
Although the process of requesting and receiving EIS documents from the Library
generally worked well, some delays in shipping, incomplete shipments and missing
volumes did occasionally occur, which resulted in delays during this phase of
the process. At one point during the data collection process, the Library physically
moved into a new building, resulting in further delay while all of their EIS
documents had been placed into boxes.
3. 2. 2 FMIS Records
The Fiscal Management Information System (FMIS) database was designed to keep
careful track of funds approved and expended on all Congressional appropriations
related to the Highway Trust Fund. The database is huge, involving more than
3 million individual records going back to the late 1940s. Each individual record
can be as long as 350 ASCII characters.
The database is maintained by FHWA, whose staff uses the information for planning
and executing program activities, evaluating program performance, and depicting
financial trends and requirements related to current and future spending. The
system provides instant access to current project data, as well as data on all
closed Federally-funded highway projects. The data included in the system is
entered in a variety of ways and from a variety of FHWA locations throughout
the country.
FMIS data is organized into two basic record types, each involving numerous
data fields. The first record type, denoted as Type 1, includes basic information
about an appropriation, such as: appropriation number; project number; project
location by state, county and MSA; a brief description of the project limits;
a brief description of project activities; when the appropriation was approved;
the date of last expenditure; etc. Additional FMIS data fields regarding environmental
documentation were added to the Type 1 records around 1990, including NEPA Class
of Action, EIS year, and EIS number. In the vast majority of the records, the
environmental information was missing from the appropriate data fields, particularly
for those records predating 1990, but also for many of the records entered after
that date. There were also many records where one or more of the other data
fields were blank as well. Missing data became particularly problematic when
the descriptive fields regarding project limits and activities were left blank,
since these data are critical for relating the FMIS records to each EIS project
available from the Northwestern University Transportation Library (see Section
3. 5. 2 for details).
The second record type, denoted as Type 2, includes more detailed data about
each appropriation, including but not limited to the following:
- nature of the project area (i.e. , urban, urbanized or rural);
- type of highway (i.e. , freeway, expressway, divided or undivided);
- functional classification (i.e. , principal arterial, minor arterial,
major collector, minor collector or local);
- work class (i.e. , preliminary engineering, construction engineering,
right-of-way or construction);
- work type (an extensive list of work types as presented in Appendix B);
- length of project;
- total funding;
- total federal funding;
- FHWA Region;
- a variety of appropriation milestone dates (i.e. , date of agreement,
date reserved, date authorized, date awarded, date underway, date completed,
date received, date of last action, etc. );
- number of lanes; and
- lane miles.
A further description of the specific FMIS data elements is provided in Appendix
C. Of the Type 2 information available, the most critical data are those related
to funding and start and completion dates for various activities. These data
make it possible to obtain precise information for use in analyzing the time
and cost required for project implementation. In this regard, there is no other
comparably consistent source that exists for these data. It should be noted,
however, that there is also an enormous amount of superfluous data in these
records which are not relevant to the research at hand. It is the superfluous
data that makes the overall database rather cumbersome and difficult to use.
Each record in the FMIS database, including Type 1 and Type 2 records, is based
on an appropriation which funds a specific project activity or group of activities
such as preliminary engineering, construction engineering, right-of-way acquisition,
a particular aspect or aspects of construction, etc. for a given project or
projects. These separate appropriations have been assigned their own 3-digit
appropriation numbers within the FMIS. Each record also reflects a specific
project or highway improvement. Separate 7-digit project numbers are assigned
within the FMIS to each specific project or highway improvement.
Sample Type 1 records are presented in Appendix D while sample Type 2 records
are presented in Appendix E. It should be noted, however, that the database
information presented in both appendices has been reformatted to make the data
more understandable and easy to use, since a single record taken directly from
FHWA's database consists of a string of approximately 350 ASCII characters with
no breaks between fields. The reformatted data presented in the appendices and
which was actually used for this analysis was created by first using SPSS software
to parse the data, and then Microsoft Excel software to present the data in
an understandable format. The sample data presented in the appendices also excludes
some fields of information that are extraneous to the research at hand.
The general methodology for using the FMIS database was to first request Type
1 records from FHWA's financial office on a statewide basis, and then organizing
the data to focus on the particular county or counties where a given EIS project
was found to be located. Once a project was determined to have been constructed,
then the Type 2 records that are specific to that particular project were requested
from FHWA. Details about how the Type 1 FMIS records were linked to each EIS
project are presented below in Section 3. 5. 2, while details about how the
Type 1 FMIS records were linked to the Type 2 records are presented in Section
3. 5. 4.
3. 2. 3 Aerial Photography and Mapping Sources
The various publicly-available internet and commercially-available software
aerial photo and mapping databases were the primary data sources used to ascertain
whether or not a given EIS project was fully constructed and is currently operating
as intended. The three data sets used in this regard are as follows:
- This internet site provides aerial photography that generally dates from
1980 to 1998 and USGS topoquad mapping. The aerial photography consists of
three basic types: Orbital Imaging, Spin-2 Satellite Imaging, and USGS aerials.
All three aerial types are provided at a resolution of 16 meters per pixel
length, although zooming to a resolution of 1 meter per pixel length is possible.
This data source can be requested at the county and/or municipal level, depending
on location. It should be noted that the actual availability of each of these
aerial photo types and the USGS topoquad mapping varies by location, as does
the date of each image.
- This internet site provides street mapping by county or municipality, and
reflects localized mapping based on U. S. Bureau of Census Tiger Files from
1990. In many cases, the 1990 files have been updated to a more recent year.
Some files were noted to have been updated as recently as 1999. Similar to
the information, the mapping is provided at a resolution of 16 meters per
pixel length, although zooming to a resolution of 1 meter per pixel length
is possible.
- MapPoint 2000 — This commercially-available CD ROM software generally provides
more detailed, and usually more current mapping based on U. S. Bureau of Census
Tiger Files from 1990. Similar to the other data sources, the mapping is provided
at a resolution of 16 meters per pixel length, although zooming to a resolution
of 1 meter per pixel length is possible.
Details about how these data sources were used in conjunction with other information
to identify whether or not an EIS project has been constructed and is currently
operating are provided in Section 3. 5. 3 below.
3. 3 Limitations of Available Data
Although the three major data sources described above provide sufficient useable
data to adequately conduct this research in the manner anticipated, several
notable limitations of these sources, as well as other sources investigated,
were found to exist which required that certain assumptions be made during the
course of the research. These data limitations are discussed below.
3. 3. 1 Start and End Dates of the EIS Process
One type of data that was found to be unavailable from any central source was
the official start and end points of the NEPA EIS process during the past 30
years. These data were necessary for identifying the total length of the NEPA
EIS process for each project. Precise dates for Notices of Intent (NOIs), which
are considered to be the official start dates of the NEPA process, and Records
of Decision (RODs), which are considered to be the official end dates of the
NEPA process, were obtainable from neither the FMIS database nor the EISs. During
the preliminary research performed for this study, inquiries were made with
FHWA headquarters, the U. S. Environmental Protection Agency (USEPA), and the
Council on Environmental Quality (CEQ) to determine if there is a central source
for these dates, and determined that such a source does not exist.
A physical check of the Federal Register was also conducted to determine
the potential for using that source. The Federal Register was found to
be available on the World Wide Web from 1995 to the present at the following
address: http://www.gpoaccess.gov/fr/index.html.
This is a searchable form of the Federal Register with a browse feature
by term and by year. For entries prior to 1995, however, a hard-copy search
must be performed in a Federal repository.
Further complicating a physical search is the change in indexing that occurred
in 1984. Environmental Impact Statements are listed as a heading in the Congressional
Information Services, Inc. (CIS) Federal Register Index which began its
publication in 1984. Prior to that year, there is no such listing in the annual
or quarterly Federal Register indexes. In the CIS Federal Register
Index, EISs are listed under the Federal Highway Administration as "Hwy
construction project plan, County State. EIS required." However, this information
is only applicable to the Notices of Intent, as no such notation was available
either prior to or after 1984 in either the standard Federal Register Index
or the CIS Federal Register Index for Records of Decision.
For the sample projects tested during the preliminary research performed for
this study, the ROD dates could not be found in the Federal Register
for any of them. Even using the date of the signed FEIS to target a date for
the ROD, the actual ROD date could not be verified using the Federal Register.
It was, therefore, concluded that searching hard copies of the Federal Register
is not an efficient use of resources, especially given the likelihood that the
ROD date will not be listed for a given project.
In the case of NOI dates, they can generally be found on the standard Federal
Register Index, although they are very difficult to find in many cases.
Due to the fact that the headings vary over time, their locations within the
index are inconsistent, often requiring hours to find a single specific entry.
Total reliance on the Federal Register Index for identifying NOI dates,
therefore, was considered to be a rather inefficient exercise, especially given
that a reasonable surrogate date could be developed.
The possibility of uniformly contacting FHWA division offices to obtain dates
for NOIs and RODs was considered during the preliminary research effort for
this study. Based on previous experience with these types of inquiries, however,
it was concluded that this would not have been a cost-effective option because
of the time required to find the person who has the information, institutional
memory problems, and the possibility that uneven data, and consequently statistical
bias, would result. Given these limitations, the effort involved in uniformly
attempting to solicit this information was concluded to be not worthwhile, even
if the information was able to be obtained part of the time.
It was also concluded that the EIS data presented in the FMIS database was
sketchy, at best. As discussed previously, the EIS data field was not included
in FMIS until 1990. Therefore, for all projects that preceded 1990, which would
constitute the majority of the projects considered as part of this research,
the FMIS database would be of no value in identifying start and end points for
the EIS process. For those projects that were entered onto the FMIS database
after 1990, it was found that data were only sporadically included in the EIS
data fields. It was also unclear exactly what data was actually reflected in
the "EIS year" field, although it is likely that the field reflects
year of EIS completion rather than year of EIS initiation. For these reasons,
the FMIS database was concluded to be of little value in identifying the total
length of the NEPA EIS process for each project.
Therefore, it was decided that the start and end points of each EIS project
should be based directly on information available in the EIS documents themselves.
Of these, the end points were easy, given that every FEIS document has an FHWA
signature date identifying when the FEIS was completed. The year of the signature
was selected as the end point, rather than arbitrarily attempting to add some
additional time period (probably a few months) after the signature date to reflect
the ROD date. Although it is likely that most RODs were approved within a few
months of the signature date, there is no basis to verify that assumption, without
conducting a statistical analysis to further test the assumption. Therefore,
the EIS end date used for each of the projects included in the research sample
was the date of signature. Only the year of the signature was recorded for use
in the analysis.
Identification of the EIS start dates, however, required greater judgement
on the part of the EIS reviewers. Since most of the EIS documents included some
sort of project history or milestones discussion, a real or proxy start date
was generally able to be identified. In a few cases, the actual date of the
NOI was reported in the EIS, but in most cases, the start date had to be estimated
based on other information presented in the project history. For instance, if
reference was made to the date of a scoping meeting or an initial project meeting,
the date of project initiation was assumed to be similar. Given that only the
year of project initiation was recorded for use in the analysis, this seems
to have been a reasonable assumption. In every case, there was some indication
provided in the EIS document that allowed a reasonable estimate to be made about
the EIS start date.
Although it is recognized that more judgement is involved in identifying the
start of the EIS process in this manner than would exist if a detailed review
of Federal Register documents were conducted for every project, the level of
effort required to do the more detailed analysis was cost and time prohibitive.
It is unlikely that the real start date for the EIS process would vary by more
than one year in either direction from that shown for each project, and it is
probable that even if there was a few month difference between the real date
and the date inferred from the EIS document, that both dates would fall within
the same recorded year. Therefore, the length of the EIS process as estimated
in this study is considered to be reasonable for analysis, although it does
not specifically reflect the time between date of signature and receipt of ROD.
3. 3. 2 Cost of the NEPA Process
Detailed project cost data is generally available in the FMIS database, beginning
with preliminary engineering and proceeding through project completion. However,
there is little information concerning the cost of the NEPA process itself,
and any planning that occurred before the NEPA process. Although the FMIS database
includes some categories for project planning prior to engineering, none of
the FMIS project data reviewed during the preliminary research contained any
such costs. As a general rule, NEPA documentation costs are included in preliminary
engineering budgets, and cannot easily be separated out.
It is theoretically possible to provide a very rough estimate of the cost of
the NEPA process using a series of wide cost ranges, based upon the number of
documents and the number of agencies involved. However, the development of such
a cost estimate would be extremely subjective and the utility of such a crude
method for estimating cost would be questionable. Because time appears to be
the principal concern of the NEPA process, the costs of the process itself have
been given a lower priority. Therefore, no effort was made to develop a cost
estimate of the NEPA documentation process for a particular project, unless
the cost was specifically included in the FMIS database. Even then, costs would
only have been included for those projects studied since 1990. In reality, NEPA
cost information was unavailable for any of the sample projects included in
this research.
3. 3. 3 Cost of Other Phases of EIS Projects
As mentioned in Section 3. 2. 2 above, the FMIS records contain information
about milestone dates and costs associated with various phases of the project
development process (i.e. , preliminary engineering, construction engineering,
right-of-way acquisition, and construction), as well as other information. Although
the milestone dates and cost information are usually provided for each individual
record (i.e. , combined appropriation number and project number), an underestimation
of total cost by EIS project is anticipated to have occurred due to the unavailability
of certain descriptive information in the FMIS records required to link those
records by EIS project. Details about the process required to identify and link
the FMIS records on the basis of a particular EIS project are provided in Section
3. 5. 2.
The descriptive data field of each FMIS record usually includes some identifying
reference to the particular segment of highway represented by a particular appropriation
number / project number combination. However, if the descriptive data field
has been left blank, there is no way to relate that particular FMIS record to
the overall EIS project. Therefore, any FMIS records in which the descriptive
data field has been left blank are essentially ignored as part of this research
assignment since they are of little value without being able to relate them
to a specific EIS project. It is estimated that such records represent less
than 10% of the total records, although a thorough assessment in this regard
was not performed.
The problem with ignoring these records is that they do contain cost information
by appropriate project development phase(s) which would not be counted in the
research. For instance, if a particular record with missing descriptive information
includes a cost value for preliminary engineering, that record may, in fact,
be associated with part of an overall project addressed in an EIS document,
but the cost for that record would not be added to the other records comprising
that EIS project. In this manner, the total cost of preliminary engineering
would be undercounted for the overall EIS project. Obviously, as the number
of FMIS records with missing descriptive information that should have been included
as part of the overall EIS project database increases, the more undercounting
that would occur. Although there is no way of estimating how many applicable
FMIS records may have been ignored or how many EIS projects may have been undercounted,
there is a likelihood that at least some of the project costs have been understated
to some extent. Therefore, some caution is urged when evaluating the results
of the impact of the NEPA process on project costs by phase.
Concerns regarding milestone dates related to unassigned FMIS records are less
of an issue than costs. Because many of the milestone dates for individual records
are included within the range of dates for all records encompassing an EIS project,
it is unlikely that there are any important dates that have not already been
incorporated. Therefore, the analysis of the impact of the NEPA process on project
schedules by phase should not be compromised in any manner due to missing data
and unassigned FMIS records.
3. 3. 4 Environmental Permitting Information
During the preliminary research performed as part of this study, it was concluded
that, unlike Northwestern University's Transportation Library in the case of
EISs, no central source for obtaining copies of environmental permits for specific
projects exists. Although the focus of this research effort has always been
to provide benchmarks related to the NEPA process rather than to emphasize delay
and cost contributions associated with environmental permitting, any information
regarding such permitting is considered to be useful in understanding interrelationships
of NEPA with other factors and processes. An indication of the likelihood that
environmental permits were actually acquired for a given project was possible
on the basis of reviewing the EIS documents associated with that project. Verification
of the receipt of such permits and details of the permit requirements, however,
can only be provided through a review of the actual permit materials. Due to
the unavailability of the permit documents from a centralized location, a simple
identification of whether or not a particular permit (e. g. , Section 404 Wetlands
Permit, U. S. Coast Guard Bridge Permit, etc. ) was required for a project was
noted during the EIS reviews. It should be noted that this limitation in data
availability is not considered to be a critical shortcoming to the intent or
implementation of this research.
3. 4 Selection of the Research Sample
As discussed in Section 3. 2. 1 above, the Transportation Library at
Northwestern University, which has an on-line internet service purportedly identifying
all of the FHWA EIS projects prepared since inception of NEPA, served as the
basis for selecting a representative sample of FHWA EIS projects for analysis
as part of this study. In effect, the Library's total database of approximately
4,000 EIS projects served as the universe from which the research sample was
drawn.
It was determined from the outset that a sample size of 100 projects was desirable
from both statistical and cost perspectives. In fact, such a sample size was
the smallest considered to be acceptable in terms of minimizing sampling error.
Referring to the widely-used Central Limit Theorem,[5] estimates of
average project delays due to NEPA should be unbiased, although some degree
of sampling error is expected. This sampling error decreases as sample size
increases. It was estimated that the sampling error associated with a sample
size of 100 projects is approximately 9. 1%, indicating that there is up to
a 9. 1% possibility that the particular sample chosen for this research could
be expected to differ from the total universe of projects. Although larger sample
sizes would result in smaller sampling error, the potential reductions in error
begin to be overshadowed by the extensive additional cost and effort required
to collect data and analyze for a larger sample size. Trading off the cost of
sampling and analysis versus the degree of estimated statistical error, it is
considered that an error of less than 10% is acceptable for this research study.
Therefore, a sample size of 100 projects is believed to provide a reasonable
level of statistical validity at a reasonable cost.
The data from the Library's World Wide Web site, which was available at a statewide
level, was downloaded and categorized according to each of the nine regions
formerly used by FHWA. The projects were then sorted by year within each region,
and then numbered to allow for random number selection within each region. As
part of the stratified random sampling process, the 100-project sample was disaggregated
into the nine separate regions, with 11 projects to be included in each in order
to ensure geographic diversity. Since this process only resulted in 99 projects,
the 100th project was randomly selected from the entire database
and added to the appropriate region.
The original intent of the stratified random sampling process was to also stratify
the projects within each region by each of the three decades since inception
of NEPA. A further constraint was originally intended to be imposed which would
limit the number of projects to be selected from the 1970s to three within each
region, or roughly 27% of the sample. The remaining eight projects in each region
would then be split between projects from the 1980s and the 1990s. This limitation
was primarily proposed to be employed given the over-representation of NEPA
EISs in the 1970s and the fact that the EISs prepared during that decade were
dramatically different in terms of scope and requirements from those prepared
in later decades.
The first cut at developing a random stratified sample did in fact stratify
on the basis of decade as well as former FHWA region. Each of the nine regions
was initially assigned 15 randomly selected EISs using the above-stated decade
stratification, with the intention of selecting 11 projects that were found
to have been actually constructed within each. However, in most cases, additional
projects had to be added to each regional sample pool when it was found that
11 completed projects could not be selected from the initial 15. In some cases,
more than 20 documents were analyzed for a given region before the sample of
11 could be completed. As new projects were added to each initial regional sample
pool, stratification by decade was eventually eliminated although stratification
by region continued.
The stratification by decade was primarily eliminated because, in some cases,
several hundred randomly numbered projects within each region failed to produce
the necessary number of projects by decade. Since the vast majority of projects
in each region dated back to the 1970s, none of those projects could be considered
further after the initial allocation of 1970s projects was made. Many other
projects were eliminated from the random number pool when it was determined
that FEIS documents were not available from the Northwestern University Transportation
Library. Availability of an FEIS was essential since the preferred alternative
would have been described in that document.
Another reason for eliminating stratification by decade was the difficulty
in finding EIS projects prepared in the 1990s that were fully constructed. Roughly
at the midpoint of the data collection process, it was concluded that any EISs
completed between 1995 and the present were unlikely to have been constructed,
based on other projects of that vintage that had already been researched. Thus,
all projects from 1995 to the present were removed from the project pool and
replacement documents were randomly selected from the Northwestern University
Transportation Library database. All remaining projects with EISs having signature
dates in the early 1990s were then prescreened in terms of their probability
for having been fully constructed before requesting any documents from the Library,
in an effort to reduce the number of EISs requiring review.
For these reasons, stratification by region became very problematic and an
inordinate amount of additional time was determined to be required in order
to continue on that basis. Therefore, it was ultimately decided to eliminate
that constraint by allowing additional 1970s projects to be randomly selected
within each region. The final sample consisted of 38 EIS projects completed
in the 1970s, 52 EIS projects completed in the 1980s, and 10 EIS projects completed
in the 1990s. It should be noted that some of the projects that have been identified
as 1980s projects, particularly those completed in the early part of the decade,
were largely prepared during the 1970s and may be more indicative of that decade.
For purposes of this analysis, however, they are appropriately included as 1980s
projects.
By the time 100 constructed and completed projects was identified for inclusion
in the research sample and placed into the final study database, a total of
162 projects had been investigated in terms of initial EIS review and making
a construction completion determination. Most of the additional 62 projects
had been eliminated because they were determined to have not yet been fully
constructed, or construction completion could not be confirmed either way. In
a few cases, projects had to be eliminated because certain critical information
(e.g., milestone dates from the FMIS records) were found to be missing in their
entirety.
The complete list of 162 projects considered and the 100 actually selected
for the research sample is presented in Appendix F. This list presents the projects
according to former FHWA region, and also identifies those projects added to
each region after the initial 15 projects were considered.
3. 5 Data Collection Methodology
The data collection methodology consists of several basic steps, as presented
in summary in Section 3. 1. The details of each basic step are provided
in the following subsections.
3. 5. 1 Initial Review of EIS Project Details
Upon receipt of each set of EIS documents from the Northwestern University
Transportation Library, they were reviewed in a cursory fashion to determine
the specific parameters of each project (e. g. , type of project, limits of
project, location of project, etc. ). If the project consisted of multiple components
(e. g. , a roadway widening and a new interchange), they were noted. Graphics
included in the EIS documents were particularly useful. It should be noted that
this review focused on the design of the preferred alternative as stated in
the FEIS, as it was assumed that the other alternatives identified were not
ultimately designed and constructed.
3. 5. 2 Linking FMIS Type 1 Records to EIS Projects
One of the key challenges of dealing with the FMIS database was determining
how to aggregrate all relevant records on the basis of each project as identified
in an EIS. It was determined during the preliminary research conducted for this
study that the number of individual appropriation number / project number combinations
included in the FMIS records that are related to a given EIS project is often
voluminous. This is due to the fact that each individual FMIS record may only
represent one or several small aspects of work associated with the entire project
(e. g. , an appropriation for some specific types of construction along some
smaller segment of highway included as part of the overall project identified
in the EIS).
After sorting the FMIS Type 1 records by county, they were linked to a specific
EIS project (i.e. , the preferred alternative shown in the FEIS) via the Type
1 descriptive data field information provided and the dates related to those
records. When the descriptive data field in a given FMIS record appeared to
be somehow related to the overall project shown in the FEIS, then the type of
work and milestone date fields were also checked for correlation to the FEIS
project. If the location, description of work and milestone dates for a given
record all appear to coincide with the specifics of the project shown in the
FEIS, then it would be linked to that project. Similarly, all other records
having locations, descriptions of work and milestone dates that appear to coincide
with the FEIS project would also be linked to that project. Once all Type 1
records that appear to be linked to an EIS project have been identified, then
Type 2 records, which have more detailed information, would be requested from
FHWA's database.
For purposes of illustrating this process, the 20-mile circumferential Route
I-287 project from Montville, New Jersey to the New York State Line is used.
This project, which was the subject of an FEIS prepared in the early 1980s,
was evaluated as part of the preliminary research conducted for this study.
Even though it is not one of the projects that was randomly selected as part
of the sample pool, the process involved in linking the FMIS Type 1 records
to the overall EIS project is similar to that used for projects included in
the pool.
In order to identify all of the FMIS Type 1 records related to the Route I-287
project from Montville, New Jersey to the New York State Line, the entire file
of Type 1 records in New Jersey first had to be opened using Excel software.
There were a total of 10,113 records in the New Jersey file. In order to make
the number more manageable, they were then sorted in the following manner:
- Records were sorted in ascending alphabetical order by the County field,
and records not pertaining to the relevant counties (i.e. , Morris, Passaic
and Bergen) were removed. This selection left 1,653 records.
- Most New Jersey projects pertaining to Interstate routes have the route
number as the first set of digits in the Project Number field (non-Interstate
routes and Interstate routes in some other states, however, do not necessarily
have obvious identifying Project Number structures). The Project Number field
was sorted in ascending numeric order and records not containing "287"
as the first three digits of the Project Number field were removed. This selection
left 134 records. For cases where route designation numbers are not part of
the Project Number field, it is necessary to rely on the descriptive information
provided in the record in order to identify the specific route or highway.
This field could be sorted or searched for numeric or text strings to produce
similar results.
- The Project Description and Work Description fields for all records pertaining
to I-287 were then reviewed and those records not pertaining to the subject
project were deleted. Judgements about which records to retain were made based
on descriptions of the geographic limits of the work in the Project Description
field and the type of work in the Work Description field. Records relating
to work on I-287 from Montville to the New York State Line were retained (examples
include descriptive entries for "Franklin Avenue to S. of Ramapo River"
or "Passaic-Bergen Cty. Line to Camp Gaw"). All records relating
to the correct geographic area of the subject project but with work items
that did not appear to be related to the project were excluded (e. g. , roadway
resurfacing). Examination of the milestone date fields was also important
to confirming the exclusion of these types of records. Of the 134 total records
related to Route I-287 as a whole, 28 were determined to be directly related
to the subject project from Montville, New Jersey to the New York State Line.
Needless to say, as the above illustrative example indicates, the process of
linking the FMIS Type 1 records to EIS projects is complex, judgmental and time
consuming. However, the process was proven to be workable and to provide reasonable
information for use in the overall research analysis.
3. 5. 3 Verification of Project Construction Completion Status
An important requirement of this research is that each project included in
the research sample be constructed to the point where it resembles the project
as proposed in the FEIS and when it is fully operational to traffic as intended.
The process of determining project completion routinely included several steps,
the first of which involved review of any available aerial photography and mapping.
The use of publicly-available internet and commercially-available CD ROM aerial
photo and mapping services was discussed as a data source in Section 3. 2. 3.
When recent aerial photography was available, analysis of the photos was useful
in determining project completion where a new facility such as an interchange,
bridge, or roadway segment was a component of the preferred alternative identified
in the FEIS document. In some cases, depending on the date of the aerial photo
and the status of completion shown to exist at that time, certain assumptions
could be made about the project's current completion status, if necessary. For
instance, if a 1998 aerial photograph showed that three out of four ramps of
an interchange project were already completed and the fourth was partially completed,
it could probably be assumed that the project has since been completed in its
entirety and is currently operating.
When aerial photography for a given project area was not available to show
whether or not the construction of the preferred alternative had been completed,
or was in fact available but did not reflect any construction completion, aerial
mapping was used if available. The problem with mapping, however, is that the
actual use of an improved facility as shown on the mapping can not necessarily
be verified. For instance, in the case of a roadway widening from four lanes
to six, mapping available through the internet and CD ROM software would not
necessarily identify that six lanes exist and are functioning. Instead, the
roadway would show up on the mapping as a major facility, but without any indication
of the number of lanes or status of widening completion. In other cases, however,
aerial mapping was sufficient for making a conclusion about project completion,
particularly when entirely new facilities were proposed.
Appendix G provides examples of aerial photography and mapping available from
the internet and CD ROM software that were used to determine whether or not
projects were actually constructed. The first example included in the appendix
presents a project that was determined not to have been constructed and operating,
while the second example presents a project that was determined to have been
constructed and is currently operating.
Another indicator of a project's completion status is the FMIS database. Since
one of the data fields in the FMIS reflects the year of construction completion,
it can be assumed that the project has been completed if all of the records
associated with a given EIS project indicate that construction has been completed.
However, if some records that have been determined to be part of the overall
EIS project show blanks in that column, then verification of construction completion
becomes problematic. When possible, this indicator was used in conjunction with
whatever aerial photography and mapping information was available.
In cases where project completion could not be verified via analysis of either
aerial photography, available mapping or FMIS records data, state transportation
agencies were contacted for project completion information. Verification in
this manner, although likely to be fairly accurate, often required random ad
hoc contacts of several individuals before finally reaching one who was actually
able to provide the information requested. The level of institutional memory
available within a state DOT was a key factor in the ability to collect valuable
input from their staffs. Where local knowledge of a project was not readily
available, or in cases where a project was constructed in an area not familiar
to local DOT staff, verification of construction completion could not be verified
in a timely manner. Record keeping issues and the lack of availability of EIS
documents at the state DOT level were found to be particularly problematic for
older projects. This procedure of contacting state DOTs was only used as a last
resort due to the time involved in locating a knowledgeable individual, and
so as not to burden the state DOT staff with specific questions about a project
that may be a distant memory.
Other difficulties in establishing construction completion were also encountered
during the course of the data collection. For instance, some of the older EISs
had very little graphic information with which to establish the construction
details needed to determine if the project was indeed built. In cases such as
the Hammond Railroad Relocation in Indiana, the FEIS document had been reproduced
at a quality too low to capture the rail lines. Project completion was impossible
to determine even with the existence of some FMIS records related to the project.
3. 5. 4 Connecting the FMIS Type 1 Records to Type 2 Records
As described in Section 3. 5. 2 above, FMIS Type 1 records have unique Appropriation
and Project Numbers for each project documented by FHWA. Once a Type 1 record
has been linked to the project detailed in an EIS, Type 2 records are obtained
from FHWA's Finance Division using the pertinent Appropriation and Project Numbers.
This process requires FHWA staff to program the database to extract the pertinent
records and provide them in ASCII format. They are then parsed for evaluation
so that the necessary data can be gathered.
As discussed in Section 3. 2. 2, the Type 2 records provide more detailed information
about each expenditure that is broken into categories such as preliminary engineering,
landscaping, right-of-way acquisition, paving, safety, etc. For every Type 1
record, there may be several or even many Type 2 records having the same combination
of Appropriation and Project Number. Matching the Type 1 and Type 2 records
proved to be a tedious and often convoluted process.
An example of a typical set of Type 1 and Type 2 records is presented in Figure
1. As seen in the figure, the Type 1 records acquired from FHWA's database are
comprised of 16 data fields. Two separate Type 1 records are shown, each having
the same Appropriation Number but different Project Numbers. Upon requesting
Type 2 records on the basis of those two Appropriation Number and Project Number
combinations, a total of six separate Type 2 records appear, four exhibiting
the first number combination and two exhibiting the second combination.
FIGURE 1: FMIS Type 1 and FMIS Type 2 Records
FMIS Type 1
|
REC-TYPE
|
STATE
|
APPROP
|
PROJECT
|
OK
|
LOCATION
|
WORK
|
NEPA
|
EISYR
|
EISNO
|
CON-TROL
|
V151
|
MSA
|
COUNTY
|
APPYR
|
LAST EXP
|
|
1
|
24.0 |
075 |
9057003 |
X |
MD 16.W.OF PARSONS CRK. BRDG.TO SLAUGHTER CREE |
GRADE, DRAIN & PAVE |
#NULL! |
.00 |
.0 |
1 |
.00 |
 |
DORCHESTER |
72.0 |
.0 |
|
1 |
24.0 |
075 |
9057004 |
X |
MD
16.PARSONS CREEK TO
SLAUGHTER CREEK BR. |
RIGHT
OF WAY ACQUISITION |
#NULL! |
.00 |
.0 |
1 |
.00 |
|
DORCHESTER |
71.0 |
.0 |
FMIS Type 2
|
TYPE |
STATE2 |
APP2 |
PROJECT2 |
LINE_ NO |
CTY_ CODE |
URB_ RURL |
FAC_ TYPE |
FUNC_ CLA |
WORK_ CLA |
WORK- TYPE |
EXPEND1 |
STEP |
MILES |
TOT_COST |
FED_FUND |
|
2 |
24.0 |
075 |
9057003 |
30.0 |
19.00 |
R |
|
|
3 |
I000 |
#NULL! |
9 |
197.00 |
6574050.00 |
3298860.00 |
|
2 |
24.0 |
075 |
9057003 |
31.0 |
19.00 |
R |
|
|
3 |
Y060 |
#NULL! |
9 |
.00 |
152390.00 |
57260.00 |
|
2 |
24.0 |
075 |
9057003 |
32.0 |
19.00 |
R |
|
|
3 |
Y080 |
#NULL! |
9 |
.00 |
5010.00 |
2510.00 |
|
2 |
24.0 |
075 |
9057003 |
.0 |
#NULL! |
|
|
|
|
|
3358630.00 |
|
.00 |
.00 |
.00 |
|
2 |
24.0 |
075 |
9057004 |
20.0 |
19.00 |
R |
|
|
2 |
ROWA |
#NULL! |
9 |
.00 |
339570.00 |
88690.00 |
|
2 |
24.0 |
075 |
9057004 |
.0 |
#NULL! |
|
|
|
|
|
88690.00 |
|
.00 |
.00 |
.00 |
 |
7071020 |
3447320 |
3. 5. 5 Final Review of EIS Project Details and Completion of Project Data
Forms
Upon making a determination that a particular project has been constructed
and is currently operating, critical information about the project and its environmental
conditions was collected from the associated set of EIS documents and recorded
on a project data form. Specific types of information that were collected and
recorded on the basis of the EIS review generally included the following:
- Project name and location;
- Project setting type;
- Project milestone dates;
- Type of improvement;
- Project size and length;
- Estimated total project cost;
- Details of NEPA process;
- Major objectives of project;
- Types of permits required;
- Types of environmental issues or controversies;
- EIS document details;
- Number of project alternatives; and
- Details of any environmental mitigation measures proposed.
In addition to the information collected from the EIS documents, pertinent
information from the FMIS records, when available, were also recorded on the
project data form for each project. The FMIS information recorded in the data
form was based on all compiled FMIS data records related to the specific EIS
project. Types of information recorded from the FMIS data records generally
included the following:
- Earliest year of agreement for a variety of project activities;
- Latest year completed for a variety of project activities;
- Total cost for a variety of project activities; and
- Federal cost for a variety of project activities.
The format and contents of the project data form template used to record the
project-specific information, which actually consists of eight separate sheets,
are shown in Appendix H. This template was developed at the outset of the research.
It should be noted, however, that the actual information collected and recorded
on the data form varied by project, especially as the research proceeded and
the potential for obtaining certain information from each EIS or set of FMIS
records became clearer. Some of the information originally proposed for collection
in the project data form was determined to be too difficult to obtain or too
subjective for undertaking statistical analysis and was therefore not collected
beyond the initial set of documents reviewed during the preliminary research.
It was also found that many of the data categories included from the FMIS records
were rarely completed and were therefore eliminated from future data collection
efforts as well.
3. 5. 6 Development and Verification of Database
The information from the project data forms was entered into a Microsoft Access
database format that was suitable for statistical handling and analysis. A total
of 197 separate data fields of information, reflecting the types of information
included on the project data forms, were initially created. However, as discussed
in Section 3. 5. 5 above, many of the data fields were dropped when it was determined
that they added little value to the analysis. An abbreviated database consisting
of 78 data fields was then developed, from which a final database of 74 variables
was created. A list of the variable names assigned to each of the abbreviated
78 data fields used and their respective definitions is provided in Table 1.
The actual final database that was created for each of the 100 projects included
in the research sample grouped by the final 74 variables is presented in Appendix
I.
Whenever a project was missing data for a given variable, the entry was generally
coded with a "999" so that it would be excluded from any statistical
analysis. For many of the original variables included in the database, the vast
majority of the entries were coded with "999" and therefore, these
variables were generally eliminated from further analysis. The variables that
made it into the final database usually had substantially fewer "999"
entries.
It should be noted that all of the cost variables included in the final database
were standardized to 1999 dollars using the Consumer Price Index (CPI). The
basic formula used in this regard is shown below:
(Cost x CPI 1999)= 1999 Cost
(CPI from Cost Year)
It was important to standardize these values since the costs as included in
the FMIS records reflect 30 separate years of data. By standardizing the data,
inflationary increases that have occurred during those years can be taken into
account. The costs included in the database as shown in Appendix I reflect the
standardized values.
Once all of the data were entered into the final database, a visual quality
control check was performed on the data to identify any anomalies such as milestone
dates that didn't make sense in relation to other milestone dates. When necessary,
the original data sources were consulted to verify that the data entered were
correct. If a transcription error was identified, the entered data was corrected.
If the data anomalies could not be explained or corrected, the data field entry
was changed to "999" in order to delete the data from further analysis.
Upon completion of the visual quality control check, the database was ready
for undertaking statistical analysis.
Table 1:
Final Database Variables and Their Definitions
|
FHWAREG
|
FHWA Region
|
|
PROJNAME |
Project Name
|
|
PROJABBR
|
Project Abbreviation
|
|
INCEPTION
|
The year the project
began.
|
|
BEG_NEPA
|
The year the NEPA
process began.
|
|
CITY1
|
The city where the
project was built.
|
|
CITY2
|
An additional city
where the project was built.
|
|
COUNTY1
|
The county where
the project was built.
|
|
COUNTY2
|
An additional county
where the project was built.
|
|
COUNTY3
|
An additional county
where the project was built.
|
|
STATE1
|
The state where the
project was built.
|
|
STATE2
|
An additional state
where the project was built
|
|
STATE3
|
An additional state
where the project was built
|
|
LAND_USE
|
Urban, suburban or
rural land use.
|
|
MSA
|
A determination whether
the project took place inside or outside a Metropolitan Statistical Area.
|
|
GROWTH
|
A determination whether
the county where the project was constructed was experiencing slow, moderate,
or rapid growth or a decline in population.
|
|
PROJTYP1
|
Project Type such
as a new or widened highway, a new interchange or bridge, etc.
|
|
PROJTYP2
|
If the project had
more than one major component, the second was listed here.
|
|
NEWLANES
|
The number of new
lanes added by the construction of the project.
|
|
LENGTH
|
the length of the
project.
|
|
LAND_AQ
|
The acres of last
acquired for the project.
|
|
EIS_COST
|
The cost of the project
as estimated in the FEIS.
|
|
FMISTOTL
|
The total dollar
amount of the FMIS Type 2 records found to be a component of the project.
|
|
FMIS_FED
|
The portion of the
FMISTOTL identified as federal expenditures in the FMIS Type 2 records.
|
|
NEPA_COA
|
NEPA class of action.
|
|
DEIS_YR
|
The year the Draft
EIS was signed.
|
|
SDEIS_YR
|
The year the supplemental
DEIS was signed. (If applicable. )
|
|
FEIS_YR
|
The year the Final
EIS was signed.
|
|
SFEIS_YR
|
The year the Supplemental
FEIS was signed. (If applicable. )
|
|
LASTEIS_YR
|
The year the latest
EIS document was signed.
|
|
PH_NO
|
The number of public
hearings held during the EIS process as recorded in the EIS.
|
|
FED_AGEN
|
The number of federal
agencies that commented on the DEIS.
|
|
ST_AGEN
|
The number of state
agencies that commented on the DEIS.
|
|
EPA_RATE
|
The EPA rating of
the DEIS.
|
|
SECT404
|
Whether or not a
Section 404 was filed for the project.
|
|
PERMCG
|
Whether or not a
US Coast Guard permit was filed for the project.
|
|
SECT4F
|
Whether of not a
Section 4-F was filed for the project.
|
|
SECT106
|
Whether of not a
Section 106 was filed for the project.
|
|
YROPEN
|
The year the project
was open to traffic as estimated from the FMIS Type 2 records.
|
|
AUTHPLAN
|
The earliest year
planning was listed as authorized for the project in the FMIS Type 2 records.
|
|
AUTHPENG
|
The earliest year
preliminary engineering was listed as authorized for the project in the
FMIS Type 2 records.
|
|
AUTHCENG
|
The earliest year
construction engineering was listed as authorized for the project in the
FMIS Type 2 records.
|
|
AUTHROWA
|
The earliest year
right-of-way acquisition was listed as authorized for the project in the
FMIS Type 2 records.
|
|
AUTHCONS
|
The earliest year
construction was listed as authorized for the project in the FMIS Type
2 records.
|
|
COMPPENG
|
The latest year preliminary
engineering was listed as completed for the project in the Type 2 records.
|
|
COMPCENG
|
The latest year connstruction
engineering was listed as completed for the project in the Type 2 records.
|
|
COMPROWA
|
The latest year acquisition
of right-of-way was listed as completed for the project in the Type 2
records.
|
|
COMPCONS
|
The latest year construction
was listed as completed for the project in the Type 2 records.
|
|
TOT$PENG
|
The total dollar
amount of preliminary engineering when the FMIS Type 2 records were totaled,
indexed to 1999 dollars (also denoted as PENG99).
|
|
TOT$CENG
|
The total dollar
amount of construction engineering when the FMIS Type 2 records were totaled,
indexed to 1999 dollars (also denoted as CENG99).
|
|
TOT$ROWA
|
The total dollar
amount of right-of-way acquisition when the FMIS Type 2 records were totaled,
indexed to 1999 dollars (also denoted as ROWA99).
|
|
TOT$CONS
|
The total dollar
amount of construction when the FMIS Type 2 records were totaled, indexed
to 1999 dollars (also denoted as CON99).
|
|
EISPP
|
The number of pages
of the EIS. (This figure was not ultimately used for analysis. )
|
|
PUBLICM
|
The number of public
meetings held with regard to the project.
|
|
AGNCYMTG
|
The number of agency
coordination meetings held for the project.
|
|
NEPACOST
|
The estimated cost
of the NEPA process. (This figure was ultimately not used for analysis.
)
|
|
ISSULAND
|
Whether or not land
use was a controversial issue in the NEPA process.
|
|
ISSUFARM
|
Whether or not farmland
was a controversial issue in the NEPA process.
|
|
ISSUECON
|
Whether or not economics
was a controversial issue in the NEPA process.
|
|
ISSUNOIS
|
Whether or not noise
was a controversial issue in the NEPA process.
|
|
ISSUAQ
|
Whether or not air
quality was a controversial issue in the NEPA process.
|
|
ISSUVIS
|
Whether or not visual
impact was a controversial issue in the NEPA process.
|
|
ISSUWETL
|
Whether or not wetlands
was a controversial issue in the NEPA process.
|
|
ISSUT&E
|
Whether or not threatened
and endangered species was a controversial issue in the NEPA process.
|
|
ISSUCULT
|
Whether or not cultural
resources was a controversial issue in the NEPA process.
|
|
ISSUWQ
|
Whether or not water
quality was a controversial issue in the NEPA process.
|
|
ISSUINDR
|
Whether or not inderect
effects was a controversial issue in the NEPA process.
|
|
ISSUEJ
|
Whether or not environmental
justice was a controversial issue in the NEPA process.
|
|
ISSUCOM
|
Whether or not community
cohesion was a controversial issue in the NEPA process.
|
|
ISSUOTHR
|
Whether or nor another
issue was controversial during the NEPA process.
|
|
PROJALT
|
The number of major
project alternatives in the FEIS.
|
|
CHGMIS
|
Whether or not the
preferred alternative changed after the MIS. (Ultimately this variable
was excluded from analysis.)
|
|
CHGDEIS
|
Whether or not the
preferred alternative changed after the EA. (Ultimately this variable
was excluded from analysis.)
|
|
CHGFEIS
|
Whether or not the
preferred alternative changed after the DEIS.
|
|
RELHH
|
The number of households
relocated.
|
|
RELBUS
|
The number of businesses
relocated.
|
|
RELOTHER
|
The number of relocations
other than those listed required during the construction of the project.
|
|
ACWETLI
|
Acres of wetlands
acquired.
|
|
Source: The
Louis Berger Group, Inc. , 2000.
|
3. 6 Statistical Analysis Methodology
The statistical analysis methodology consists of several basic steps, as presented
in summary in Section 3. 1. The details of each basic step are provided in the
following subsections.
3. 6. 1 Identification of Descriptive Statistics
Descriptive parameters of the database variables were developed, first as a
means to identify the general characteristics of each variable and then as a
method of identifying any further anomalies in the data that were not caught
during the visual quality control check as discussed in Section 3. 5. 6. above.
In this regard, the final database was entered into the SPSS Base 10 statistical
software package, which allows a variety of descriptive statistical analyses
to be performed.
The database was initially examined to determine if any values fell outside
of a range of values that was considered to be appropriate for a given variable.
Any values that suggested a potential error in the data or a suspicious outlier
were identified and flagged for further scrutiny. These values were then examined
in relation to the mean, standard deviation, skewness, range, and maximum and
minimum values of continuous data variables. Histograms, stem-and-leaf, and
box-and-whisker plots were created to provide a visual view of the data (examples
of these types of graphic representations are provided in Appendix J). Probability
plots, used to evaluate the degree to which continuous variables vary from the
normal distribution, were created for most continuous variables. In the case
of nominal variables, a frequency analysis usually sufficed to indicate any
anomalies.
Next, a number of computed variables were created from the variables included
in the final database. One of these variables, denoted as PROSTART, was created
to reflect the earlier date of the two variables, BEG_NEPA and AUTHPENG. This
variable was necessary since some projects indicated that the NEPA process began
even before Preliminary Engineering officially began.
Most of the computed variables were created by subtracting one variable from
another and were established to create timelines. The specific variables that
were created in this manner, using some of the variables shown in Table 1, are
as follows:
|
|
= |
Length
of the NEPA process (denoted as NEPATIME); |
|
|
= |
Length
of the Preliminary Engineering process (denoted as PENGTIME); |
|
|
= |
Length of the Construction
Engineering process (denoted as CENGTIME);
|
|
|
= |
Length
of the Right-of-way Acquisition process (denoted as ROWTIME); |
|
|
= |
Length
of the Construction process (denoted as CONTIME); |
|
|
= |
Length
of the entire Project Development process from beginning of Preliminary
Engineering to the end of Construction (denoted as PENG2CON); |
|
|
= |
Length
of the entire Project Development process from Project Inception to end
of Construction (denoted as INCEP2CON); |
|
|
= |
Length
of the entire Project Development process from beginning of Preliminary
Engineering to year of Project Opening; |
|
|
= |
Length
of the Project Development process from Project Inception to Project Opening
(denoted as INCEP2OP); and |
|
|
= |
Length
of the Project Development process from the beginning of either the NEPA
process or Preliminary Engineering, whichever occurred first, to year of
Project Opening (denoted as OPMINSTR). |
In the above cases where one variable was subtracted from another, the results
were checked to ascertain if an inappropriate value resulted. For example, if
the year in which a process began was subtracted from the year in which it ended
and a negative result occurred, it indicates that the end date was earlier than
the begin date. An effort was then made to determine if there was a data entry
error or if the source data was incorrect. If the issue could not be resolved,
the case was eliminated for analyses involving either the computed variable,
the begin date or the end date.
In addition to the new variables that were created to reflect timelines, one
computed variable was created by adding one variable to another. This new variable,
which was also created by using some of the variables shown in Table 1, is as
follows:
|
|
=
|
The number
of Total Agencies involved, including both Federal Agencies and State Agencies
(denoted as ALLAGENC). |
Another variable, denoted LEISDEC, was created to reflect the decade in which
the EIS was completed (i.e., LASTEIS_YR). All cases in which the EIS was completed
in the 1970s were coded as "1970s" under the LEISDEC variable. Similar
codings were performed for those EISs completed in the 1980s and 1990s.
Finally, a number of variables were created by transforming other existing
variables into different numeric equivalents such as square roots or logarithms.
The following new variables were created in this manner:
|
|
= |
Square
root of NEPATIME; |
|
|
= |
Natural
log of TOT$PENG (PENG99); |
|
|
= |
Natural
log of TOT$CENG (CENG99); |
|
|
= |
Natural
log of TOT$ROWA (ROW99); |
|
|
= |
Natural
log of TOT$CONS (CON99); |
|
|
= |
Natural
log of FMISFED; |
|
|
= |
Natural
log of FMISTOT; |
|
|
= |
Natural
log of LANDAQ; |
|
|
= |
Square
root of PENGTIME; |
|
|
= |
Square
root of CONTIME; |
|
|
= |
Natural
log of ACWETL; |
|
|
= |
Numerical
recoding of MSA; |
|
|
= |
Numerical
recoding of GROWTH; |
|
|
= |
Numerical
recoding of LANDUSE; and |
|
|
= |
Numerical
recoding of PROJTYP1. |
It should be noted that the addition of the created variables to the database
increased the total number of variables to 114, although not all of those variables
were necessarily used in the statistics analyses.
The computed variables and the original variables were then run through the
program's Exploratory Data module, which repeated some of the descriptives,
added others (e. g. , medians, m-estimator measures, etc.) and consolidated
much of the information into a single set of tables. An additional advantage
of the Exploratory Data module is that it permits the compilation of data by
categories, so that exploratory data could be generated by former FHWA Region
and allow the results to be compared.
In developing the descriptive statistics, a number of assumptions were made.
These include the following:
- All data were drawn from a normal population;
- All cases are independent of each other;
- Significance was set at 0. 05 and, in cases where the statistical package
calculated the precise significance, it is provided; and
- Where the length of time for a process (e. g. , Preliminary Engineering
or the NEPA process) was accomplished within a single year, the process was
shown as taking one year.
3. 6. 2 Selection of Data Analysis Methods
Descriptive and analytical methods were limited to procedures available in
the SPSS Base 10 package. The specific methods used from that package are described
below.
Identification of Data Distribution
Many statistical tests require that the data being analyzed be normally distributed.
Although the Central Limits Theorem permits the normalcy requirement to be relaxed
for any sample where n$100, an effort was made to either transform non-normally
distributed data to a form approximating a normal distribution, or to test the
data using procedures that do not require a normal distribution.
Continuous data were examined for normalcy using both graphic and non-graphic
methods. First, the variable was subjected to a Kolmogorov-Smirnov test against
a theoretical normal distribution. If the significance level was greater than
0. 05, the variable was assumed to not differ significantly from the normal
distribution. If the significance level was #0. 05, the variable was treated
as being not normally distributed.
Data Transformations
Data identified as being non-normally distributed were then visually examined
using one or more histograms and probability plots to identify the most likely
transformation method. If a given variable could be appropriately transformed
using the techniques available in the statistical package, this was done. In
some cases, the square root of the original variable resulted in a normal distribution.
In other cases, the logn, log10, reciprocal or exponential
transformations were tested. Transformation resulted in a new variable, but
the original variable was retained. The key variables created through such transformation
are identified above in Section 3. 6. 1.
Parametric Versus Non-Parametric Analyses
Some variables in the final database could not be easily transformed. Others
were clearly not continuous data and, therefore, were not normally distributed.
For these variables, non-parametric test procedures were utilized. Unlike parametric
procedures, non-parametric procedures do not require a normal distribution.
Non-parametric tests are generally considered to have less power than parametric
tests (i.e. , there is a somewhat higher risk of a Type II error occurring,
which involves the failure to reject a hypothesis when it is actually false).
Since the norm in significance testing is to test a null hypothesis (e. g. ,
there is no difference in the length of the NEPA process between Regions
1 and 5), the lower power of the non-parametric tests could result in failing
to reject that hypothesis. Therefore, wherever possible, parametric tests were
used. In some cases, the transformation was tested parametrically and the original
variable was tested non-parametrically to compare the results.
3. 6. 3 Statistical Relationship Tests Between Variables
A number of statistical relationship tests were designed and conducted in order
to answer a number of questions, all of which relate to the length of the NEPA
process. Specifically, these tests were designed to identify which variables,
if any, are correlated with the length of the NEPA process, and which factors,
if any, appear to differ with respect to the length of the NEPA process. A list
of the correlations that were tested in this regard are shown in Table 2.
The general approach to identifying any statistical relationships began by
first looking at the descriptive statistics as a whole, and then by looking
at the descriptive statistics broken down by categories suggested by the data
variables themselves. For example, a total of 97 out of the 100 cases of NEPATIME
information were considered to be useable for analysis, after those cases that
were considered to be extreme outliers were eliminated. These 97 cases could
then be grouped into categories (e. g. , by FHWA region) and the descriptive
statistics could be obtained by category (FHWA region) as well. The same process
could then be followed for dividing the 97 cases into, for instance, those associated
with a Section 4(f) study and those not associated with a Section 4(f) study.
Similar analyses could be performed for a variety of other types of categories
as well.
The next step was to attempt to find significant differences in the length
of the NEPA process according to the categorical variables. Finally, any correlations
between the length of the NEPA process and other more or less continuous variables
were sought. A preliminary correlation matrix was run, relating the length of
the NEPA process to all other continuous variables. Those variables that appeared
to have a linear relationship or close to it, were selected for further analysis.
Further analysis involved either transforming those variables which could be
made to approximate the normal distribution and then correlating them to the
length of the NEPA process, or ascertaining the correlation through use of nonparametric
procedures.
Where the variables against which the length of the NEPA process were to be
tested were categorical, relationships were examined using ANOVA (Analysis of
Variance) or an Independent Sample t-test. The ANOVA was used where there were
multiple categories to be tested. The t-test, on the other hand, was used where
the categories were dichotomous. In one case (i.e. , the variable NEWLANES),
the variable was considered to be an ordinal variable, requiring that a correlation
with NEPATIME be obtained by using Spearman's Rho, a non-parametric correlation
procedure.
Table 2: Statistical Correlation Tests Conducted for the Length of the NEPA Process and a Variety of Other Variables
- (LASTEIS_YR — BEG_NEPA) and FHWAREG (1, 3 and 4 combined)
- (LASTEIS_YR — BEG_NEPA) and FHWAREG (1, 3 and 4 separately)
- (LASTEIS_YR — BEG_NEPA) and LAND_USE
- (LASTEIS_YR — BEG_NEPA) and MSA
- (LASTEIS_YR — BEG_NEPA) and GROWTH
- (LASTEIS_YR — BEG_NEPA) and PROJTYP1
- (LASTEIS_YR — BEG_NEPA) and NEWLANES
- (LASTEIS_YR — BEG_NEPA) and LENGTH
- (LASTEIS_YR — BEG_NEPA) and LASTEIS_YR ('70s, '80s and '90s separately)
- (LASTEIS_YR — BEG_NEPA) and PH_NO
- (LASTEIS_YR — BEG_NEPA) and (FED_AGEN + ST_AGEN)
- (LASTEIS_YR — BEG_NEPA) and EPA_RATE
- (LASTEIS_YR — BEG_NEPA) and SECT404
- (LASTEIS_YR — BEG_NEPA) and PERMCG
- (LASTEIS_YR — BEG_NEPA) and SECT4F
- (LASTEIS_YR — BEG_NEPA) and SECT106
- (LASTEIS_YR — BEG_NEPA) and (COMPPENG — AUTHPENG)
- (LASTEIS_YR — BEG_NEPA) and (COMPCENG — AUTHCENG)
- (LASTEIS_YR — BEG_NEPA) and (COMPROWA — AUTHROWA)
- (LASTEIS_YR — BEG_NEPA) and (COMPCONS — AUTHCONS)
- (LASTEIS_YR — BEG_NEPA) and (COMPCONS — AUTHPENG)
- (LASTEIS_YR — BEG_NEPA) and (COMPCONS — INCEPTION)
- (LASTEIS_YR — BEG_NEPA) and (YROPEN — AUTHPENG)
- (LASTEIS_YR — BEG_NEPA) and (YROPEN — INCEPTION)
- (LASTEIS_YR — BEG_NEPA) and PUBLICM
- (LASTEIS_YR — BEG_NEPA) and AGNCYMTG
- (LASTEIS_YR — BEG_NEPA) and ISSULAND
- (LASTEIS_YR — BEG_NEPA) and ISSUFARM
- (LASTEIS_YR — BEG_NEPA) and ISSUECON
- (LASTEIS_YR — BEG_NEPA) and ISSUNOIS
- (LASTEIS_YR — BEG_NEPA) and ISSUAQ
- (LASTEIS_YR — BEG_NEPA) and ISSUVIS
- (LASTEIS_YR — BEG_NEPA) and ISSUWETL
- (LASTEIS_YR — BEG_NEPA) and ISSUT&E
- (LASTEIS_YR — BEG_NEPA) and ISSUCULT
- (LASTEIS_YR — BEG_NEPA) and ISSUWQ
- (LASTEIS_YR — BEG_NEPA) and ISSUINDR
- (LASTEIS_YR — BEG_NEPA) and ISSUEJ
- (LASTEIS_YR — BEG_NEPA) and ISSUCOM
- (LASTEIS_YR — BEG_NEPA) and ISSUOTHR
- (LASTEIS_YR — BEG_NEPA) and PROJALT
- (LASTEIS_YR — BEG_NEPA) and CHGFEIS
- (LASTEIS_YR — BEG_NEPA) and RELHH
- (LASTEIS_YR — BEG_NEPA) and RELBUS
- (LASTEIS_YR — BEG_NEPA) and ACWETLI
- (LASTEIS_YR — BEG_NEPA) and EIS_COST (standardized to an index year from
LASTEIS_YR)
- (LASTEIS_YR — BEG_NEPA) and FMISTOTL (standardized to an index year from
Median year between AUTHPENG and COMPCONS)
- (LASTEIS_YR — BEG_NEPA) and TOT$PENG (standardized to an index year from
Median year between AUTHPENG and COMPPENG)
- (LASTEIS_YR — BEG_NEPA) and TOT$CENG (standardized to an index year from
Median year between AUTHCENG and COMPCENG)
- (LASTEIS_YR — BEG_NEPA) and TOT$ROWA (standardized to an index year from
Median year between AUTHROWA and COMPROWA)
- (LASTEIS_YR — BEG_NEPA) and TOT$CONS (standardized to an index year from
Median year between AUTHCONS and COMPCONS)
Notes: In some of the above cases, there was either insufficient information
available for a given variable or insufficient variety of data within the variable
to actually allow correlation tests to be performed. Therefore, the above list
presents the full listing of correlation tests that were considered, rather
than those that were actually performed.
The variable LASTEIS_YR — BEG_NEPA is also denoted as NEPATIME.
Source: The Louis Berger Group, Inc. , 2000.
|
 |