Evaluating the Performance of Environmental Streamlining:
Development of a NEPA baseline for Measuring Continuous Performance
5.0 CONCLUSIONS AND RECOMMENDATIONS
|
Previous
| Index | Next
5. 1 Conclusions
As presented in Section 4. 0, this research has resulted in a number of interesting
conclusions related to the NEPA EIS process and its relationship with other
factors, including the length of the overall project delivery process. A summary
listing of the major results is presented below:
- Based on the first 30 years of NEPA compliance, the typical length of time
for preparing an EIS pursuant to NEPA has been either 3. 0 or 3. 6 years,
depending on whether the median or mean values are used, respectively;
- The length of time for preparing an EIS pursuant to NEPA has varied between
former FHWA regions, with the greatest time required in Region 1 (4. 5 or
4. 7 years, based on median or mean values, respectively) and the least time
required in Region 10 (1. 0 or 2. 2 years, based on median or mean values,
respectively);
- For those projects in which an EIS pursuant to NEPA was required, the mean
time required for the entire project development process has been approximately
13. 1 years;
- For those projects in which an EIS pursuant to NEPA was required, the NEPA
process accounted for approximately 27 to 28% of the total time required for
the entire project development process, depending on whether the median or
mean values are used, respectively;
- The length of time for preparing an EIS pursuant to NEPA has varied between
each of the three decades that have occurred since NEPA was implemented, ranging
from a mean of 2. 2 years in the 1970s to a mean of 5. 0 years in the 1990s;
- The length of time for preparing an EIS pursuant to NEPA has varied depending
on whether or not a Section 404 permit was also required, ranging from a mean
of 2. 4 years when no Section 404 permit was required to a mean of 4. 3 years
when a Section 404 permit was required;
- The length of time for preparing an EIS pursuant to NEPA has varied depending
on whether or not Section 4(f) approval was also required, ranging from a
mean of 2. 8 years when no Section 4(f) approval was required to a mean of
4. 7 years when Section 4(f) approval was required;
- The length of time for preparing an EIS pursuant to NEPA has varied depending
on the number of agency meetings held, ranging from a mean of 2. 4 years when
fewer than three agency meetings were held to a mean of 4. 5 years when three
or more agency meetings were held;
- The length of time for preparing an EIS pursuant to NEPA has varied depending
on the number of public meetings held, ranging from a mean of 2. 7 years when
fewer than three agency meetings were held to a mean of 4. 2 years when three
or more agency meetings were held; and
- The length of time for preparing an EIS pursuant to NEPA has varied depending
on whether or not noise has been an issue, ranging from a mean of 3. 2 years
when noise was not an issue to a mean of 4. 4 years when noise was an issue.
All of the above findings serve as useful information for establishing a baseline
condition against which to evaluate future efforts to implement environmental
streamlining initiatives within the NEPA process. The fact that these findings
are based on a comprehensive analysis of historical data ensures that the baseline
conditions that have been identified reflect the best information available
for understanding the NEPA process timelines that have been experienced to date.
Although there are some limitations inherent in the data, no other better source
of information currently exists.
After a few years, when information regarding current and future projects where
new environmental streamlining initiatives are employed becomes available, they
can be compared against the findings stated above to assess whether there has
been any improvement in terms of the length of the NEPA process under a variety
of conditions. Unfortunately, it will likely require a number of additional
years before any projects in which new streamlining initiatives have been employed
actually complete the entire project development process. Nevertheless, the
baseline information presented in this report will be available and will continue
to be valid for comparing future NEPA projects, regardless of when they become
ready to make such comparison.
It should be cautioned, however, that any future comparative efforts utilize
data that are similar in nature to the data used to develop the above findings.
For instance, the values presented above for the typical length of time to prepare
an EIS pursuant to NEPA do not include the time period following signature of
the FEIS document and preceding the Record of Decision. Therefore, future efforts
should also define the end of the NEPA process as the date of FEIS signature,
although the additional time required to complete the Record of Decision can
and should be recorded as a separate data field.
5. 2 Recommendations
Since it is assumed that any efforts to collect, analyze and monitor data for
ongoing and future projects would essentially follow the same methodology used
in this research effort, the primary recommendations to be made reflect potential
improvements that could be made to the existing data sources to further enhance
such efforts. These include the following:
- Require descriptive information in FMIS records — In order
to improve upon the ability to capture and utilize a greater percentage of
the total FMIS records, it is necessary to ensure that better recordation
of descriptive information in those records is implemented. The descriptive
fields are critical to the ability to allocate each record to a given EIS
project. Although the information in the FMIS records is collectively provided
by many FHWA staff members located throughout the country, the FHWA staff
that are actually responsible for compiling and maintaining these records
could perhaps implement more specific requirements and measures for adequately
completing the information requested. These requirements and measures would
not improve the quality and usability of the existing records, but they would
certainly improve the ability to use future records.
- Reuire identification of EIS number in FMIS records — A valuable
type of data that would further improve the ability to capture and utilize
a greater percentage of FMIS records, as well as to improve the ability to
link those records to specific EIS projects, would be the inclusion of the
specific EIS number associated with each appropriation number / project number
combination. The inclusion of such data would even eliminate the need to provide
descriptive information in the FMIS records, although in combination, both
types of data would significantly improve the data collection and analysis
process. Similar to the above recommendation, the FHWA staff that are specifically
responsible for compiling and maintaining the FMIS database could implement
requirements and measures for ensuring that the FHWA field staff provide the
data in the format necessary for future analysis. Once again, these requirements
and measures would not improve the quality and usability of the existing records,
but they would certainly improve the ability to use future records.
Consideration should also be given to expanding the baseline sample in order
to further reduce the potential for sampling error. As stated in Section 3.
4, the sampling error associated with a sample size of 100 projects, as used
in this study, is approximately 9. 1%. Increasing the sample size to 150 projects
would decrease the potential for sampling error to approximately 7. 1% while
a sample size of 200 projects would reduce it to approximately 5. 8%. A sample
size of 300 projects would be required in order to reduce potential for sampling
error to only 5. 0%. Of course, a trade-off must be made between the ability
to reduce the potential for sampling error and the time and cost associated
with providing incremental statistical improvements. Although the sample used
in this study is considered to be statistically valid for the research performed,
increasing the sample size to 200 projects would further improve the statistical
validity of the results. However, if no additional research on this topic is
ever conducted, the results included herein do provide a valid and reasonable
baseline against which to evaluate future environmental streamlining efforts.
|
 |