NEPA Implementation
The Importance of Purpose and Need in Environmental Documents
    September 18, 1990
     Introduction 
        The purpose and need 
        section is in many ways the most important chapter of an environmental 
        impact statement (EIS). It establishes why the agency is proposing to 
        spend large amounts of taxpayers' money while at the same time causing 
        significant environmental impacts. A clear, well-justified purpose and 
        need section explains to the public and decisionmakers that the expenditure 
        of funds is necessary and worthwhile and that the priority the project 
        is being given relative to other needed highway projects is warranted. 
        In addition, although significant environmental impacts are expected to 
        be caused by the project, the purpose and need section should justify 
        why impacts are acceptable based on the project's importance. 
		
      As importantly, the 
        project purpose and need drives the process for alternatives consideration, 
        in-depth analysis, and ultimate selection. The Council on Environmental 
        Quality (CEQ) regulations require that the EIS address the "no-action" 
        alternative and "rigorously explore and objectively evaluate all 
        reasonable alternatives." Furthermore, a well-justified purpose and 
        need is vital to meeting the requirements of Section 4(f) (49 U.S.C. 303) 
        and the Executive Orders on Wetlands (E.O. 11990) and Floodplains (E.O. 
        11988) and the Section 404(b)(1) Guidelines. Without a well-defined, well-established 
        and well-justified purpose and need, it will be difficult to determine 
        which alternatives are reasonable, prudent and practicable, and it may 
        be impossible to dismiss the no-build alternative. 
		
      The transportation 
        planning process, which includes regional, sub-area, and corridor planning, 
        can serve as the primary source of information for establishing purpose 
        and need as well as evaluating alternatives. Information and forecasts 
        of vehicle miles of travel, travel demand, highway and travel speeds, 
        traffic diversion, time of day characteristics, and traffic accident rates 
        can be provided by the planning process. This information can be used 
        to evaluate congestion, air quality, safety, and other environmental issues 
        for various transportation alternatives including the no-build alternative. 
        Planning can also estimate the benefits and costs associated with highway 
        and transit projects that can be used in the development of project "purpose 
        and need." 
      Consideration of Alternatives 
      In urbanized areas, 
        the urban transportation planning process required by Section 134 of Title 
        23, should result in plans and programs that are consistent with the comprehensively 
        planned development of an area and that integrate transportation, land 
        use, and environmental considerations. Comprehensive planning, which includes 
        transportation, should establish the basic purpose and need for specific 
        projects and the system wide consequences of operational improvements 
        and the no-build alternative. For example, the planning process should 
        identify the need for a transportation improvement between points x and 
        y at some future date. Further, in a high percentage of cases, a decision 
        on the appropriate mode (highway or transit) and the basic project concept 
        (freeway on new location, upgrade of existing facility, light rail transit, 
        bus/high-occupancy vehicle lanes, approximate travel demand, etc.) can 
        be determined. In other cases, it may not be possible to resolve these 
        issues until the conclusion of the project development process. Scoping 
        meetings early in the environmental process are an excellent means to 
        reach agreement with the participants on the basic purpose and need for 
        the project, the consequences of the no-build alternative, and operational 
        improvements and, where possible, the mode and project concept. 
		
      After the basic purpose 
        and need for the project are established, a number of lines can theoretically 
        still be drawn to connect points x and y. If the project's purpose and 
        need are so vague as to only stipulate that a transportation improvement 
        between x and y is needed, then reasonable alternatives would cover a 
        wide range and must be evaluated to comply with the CEQ regulations. As 
        the project's purpose and need is refined, a number of alternatives will 
        drop out, thereby permitting a more focused analysis of those alternatives 
        which truly address the problem to be solved. As alternatives are dropped 
        from consideration, it is recommended that the concurrence of those cooperating 
        agencies with jurisdiction by law be sought in that decision. 
      In a similar manner, 
        the type of improvement to be considered even after the planning process 
        may be wide ranging: from upgrading an existing facility to multi-lane 
        freeway on now location. The traffic demands, safety concerns, system 
        continuity considerations, etc., all will help define reasonable alternatives 
        and products from the transportation planning process should serve as 
        a primary source for this information. 
      Beyond the CEQ regulations 
        requirement of evaluating all, or a reasonable number representative of 
        the full spectrum of reasonable alternatives, there are other more action-limiting 
        requirements for alternatives under Section 4(f), the Executive Orders 
        on Wetlands and Floodplains, and the Section 404(b)(1) guidelines. To 
        address these requirements and conclusively demonstrate that some alternatives 
        are not prudent or practicable, a well-justified purpose and need are 
        vital. 
      The use of land from 
        a Section 4(f) protected property (significant publicly owned public park, 
        recreation area or wildlife and waterfowl refuge, or any significant historic 
        site) may not be approved unless a determination is made that there is 
        no feasible and prudent alternative to such use. There are numerous factors 
        which could render an alternative "not prudent" because of unique 
        problems, including cost and environmental impacts. If an alternative 
        does not meet the project's purpose or satisfy the needs then the alternative 
        is not prudent provided the purpose and need section can substantiate 
        that unique problems will be caused by not building the project.
		
      If a proposed action 
        is to be located in a wetland or it entails a floodplain encroachment 
        with significant impacts, a finding must be made that there is no practicable 
        alternative to the wetland take or floodplain encroachment. Any alternative 
        which does not meet the need for the project is not practicable. If the 
        project's purpose and need are not adequately addressed, specifically 
        delineated and properly justified, resource agencies, interest groups, 
        the public or others will be able to generate one or possibly several 
        alternatives which avoid or limit the impact and "appear" practicable. 
        Sometimes long, drawn out negotiations or additional analyses are needed 
        to clearly demonstrate that an alternative is not practicable, where a 
        well-described justification of the project's purpose and need would have 
        clearly established it. 
		
      If an alternative 
        does not satisfy the purpose and need for the project, as a rule, it should 
        not be included in the analysis as an apparent reasonable alternative. 
        There are times when an alternative that is not reasonable is included 
        based on the request of another agency or due to public expectation. In 
        such cases, it should be clearly explained why the alternative is not 
        reasonable (or prudent or practicable), why it is being analyzed in detail 
        and that because it is not reasonable that it will not be selected. 
    Basic Ingredients of Purpose and Need
      The purpose and need 
        should be as comprehensive and specific as possible. For example, rather 
        than simply stating that additional capacity is needed between two points, 
        information on the adequacy of current facilities to handle the present 
        and projected traffic, (e.g., what capacity is needed and the level of 
        service for the existing and proposed facilities) should be discussed. 
        Other information on factors such as safety, system linkage, social demands, 
        economic development, and modal interrelationships, etc., that the proposed 
        project will attempt to address, should be described as fully as possible. 
        This will assist in pinpointing and refining the alternatives which should 
        be analyzed. Further, it will in a sense "protect" those viable 
        alternatives from sniping by external interests and capricious suggestions 
        to study something else. If the purpose of and need for the proposed project 
        are rigorously defined, the number of "solutions" which will 
        satisfy the conditions can be more readily identified and narrowly limited. 
      
      The purpose and need 
        section of the project may, and probably should, evolve as information 
        is developed and more is learned about the project and the corridor. For 
        example, assume that the only known information with regard to purpose 
        and need is that additional capacity is needed between points x and y. 
        At the outset, it may appear that commuter traffic to a downtown area 
        is the problem and only this traffic needs to be served. A wide range 
        of alternatives may meet this need. As the studies progress, it may be 
        learned that a shopping center, university, major suburban employer, and 
        other traffic generators contribute substantially to the problem and require 
        transportation service. In this case, the need is further refined so that 
        not only commuter trips but also student, shopping, and other trips will 
        be accommodated. 
      These refinements 
        would clearly reduce and limit the number of alternatives which could 
        satisfy the project's purpose and need, thereby reducing the number and 
        range of reasonable, prudent and practicable alternatives. If an alternative 
        is suggested that does not serve the university or other traffic generator, 
        and such service is a vital element of the project, the alternative may 
        be eliminated from future study since it does not meet the need for the 
        project. 
      In the example above, 
        it should be noted that products of the urban transportation planning 
        process should identify many of the elements which contribute to the transportation 
        problems. To the extent that the planning process develops these products 
        and these products are utilized in project development, it may not be 
        necessary to prepare additional studies. 
      Some of the elements which may assist in explaining a project's purpose and need (e.g., capacity, 
        safety, system linkage, etc.), are described on page 14 of  FHWA Technical Advisory T 6640.8A - "Guidance for Preparing and Processing Environmental 
        and Section 4(f) Documents."  This discussion is included here as 
        an appendix. All of the elements which are relevant should be as fully 
        developed as possible and utilize as specific data as possible to compare 
        the present, future no-build, and future build conditions. Data should 
        be presented on such factors as reduction in vehicle hours of travel, 
        improvements in travel speeds on the system, reduction in traffic accidents, 
        injuries and fatalities, savings in cost to the traveling public, enhanced 
        economic development potential, increased tax bass, improved access to 
        public facilities, etc. It is not sufficient to state that the project 
        is needed to provide increased capacity and improve safety. Supporting 
        data must be provided. 
Using 
        Purpose and Need in Decisionmaking        
      As noted above, the 
        purpose and need define what can be considered reasonable, prudent, and 
        practicable alternatives. The decisionmaking process should first consider 
        those alternatives which meet the purpose and need for the project at 
        an acceptable cost and level of environmental impact relative to the benefits 
        which will be derived from the project. 
      At times, it is possible 
        that no alternative meets all aspects of the project's purpose and need. 
        In such a case, it must be determined if the alternatives are acceptable 
        and worthwhile pursuing in light of the cost, environmental impact and 
        less than optimal transportation solution. To properly assess this, it 
        is important to determine the elements of the purpose and need which are 
        critical to the project, as opposed to those which may be desirable or 
        simply support it, the critical elements are those which if not met, at 
        least to some minimal level, would lead to a "no-build" decision. 
        Determining critical needs could include policy decisions as well as technical 
        considerations. 
      Other times, the cost 
        or level of environmental impact are not acceptable and an alternative 
        that only partially meets the purpose and need or the no-build alternative 
        must be considered. If the costs are justified in relation to the transportation 
        benefits, then a less than full-build alternative may be acceptable. 
      In the vast majority 
        of cases, however, at least one alternative will fully meet the purpose 
        and need at an acceptable cost and level of impact. In cases where more 
        than one alternative fully meets the purpose and need, a number of factors 
        including cost, traffic service, safety, public support, environmental 
        impact, etc., will be considerations in reaching the decision on which 
        is the preferred alternative. The requirements of Section 4(f), the Wetland 
        and Floodplain Executive Orders, and the Section 404(b)(1) guidelines, 
        of course, play an important role in this process. 
Key  Points to Remember  
      In summary, the purpose 
        and need section in the EIS lays out why the proposed action, with its 
        inherent costs and environmental impacts, is being pursued. If properly 
        described, it also limits the range of alternatives which may be considered 
        reasonable, prudent, and practicable in compliance with the CEQ regulations, 
        Section 4(f) the Executive Orders on Wetlands and Floodplains, and the 
        Section 404(b)(1) guidelines. Further, it demonstrates the problems that 
        will result if the project is not implemented. 
      There are three key 
        points to remember relative to the purpose and need section of an EIS. 
        It should be: 
       
        - justification of why the improvement must be implemented;
-  as comprehensive and specific as possible; and,
- reexamined and updated as appropriate throughout the project development 
          process.
Appendix
        The following is a list of items which may assist in the explanation of 
        the need for the proposed action. It is by no means all-inclusive or applicable 
        in every situation and is intended only as a guide. 
      
        - Project Status - Briefly describe the project history including actions 
          taken to date, other agencies and governmental units Involved, actions 
          pending, schedules, etc.
- System Linkage - Is the proposed project a "connecting link?" 
          How does it fit in the transportation system?
- Capacity - Is the capacity of the present facility inadequate for 
          the present traffic? Projected traffic? What capacity is needed? What 
          is the level(s) of service for existing and proposed facilities.
- Transportation Demand - Including relationship to any statewide plan 
          or adopted urban transportation plan together with an explanation of 
          the project's traffic forecasts that are substantially different from 
          those estimates from the 23 U.S.C. 134 (Section 134) planning process.
- Legislation - Is there a Federal, State, or local governmental mandate 
          for the action.
- Social Demands or Economic Development - New employment, schools, 
          land use plans, recreation, etc,. What projected economic development/land 
          use changes indicate the need to improve or add to the highway capacity?
- Modal Interrelationships - How will the proposed facility interface 
          with and serve to complement airports, rail and port facilities, mass 
          transit services, etc.?
- Safety - Is the proposed project necessary to correct an existing 
          or potential safety hazard? Is the existing accident rate excessively 
          high? Why? How will the proposed project improve it?
- Roadway Deficiencies - Is the proposed project necessary to correct 
          existing roadway deficiencies (e.g., substandard geometrics, load limits 
          on structures, inadequate cross-section, or high maintenance costs)? 
          How will the proposed project improve it?